Focus on resolving land acquisition issues for National Highway 14E project

(QNO) - After inspecting the site of the project to renovate and upgrade National Highway 14E, the section through Thang Binh and Hiep Duc districts on June 11, Vice Chairman of the Provincial People's Committee Tran Nam Hung continued to direct the removal of obstacles in compensation and site clearance for the project.

Báo Quảng NamBáo Quảng Nam17/06/2025

0.jpg
Comrade Tran Nam Hung (standing 3rd from the left) listened to Thang Binh district report on land acquisition problems at the railway overpass construction site on June 11. Photo: CONG TU

The provincial People's Committee leaders assessed that the progress of compensation and site clearance (GPMB) is still slow, directly affecting the construction progress as planned. There is very little time left, the provincial government requested the People's Committees of Thang Binh and Hiep Duc districts to identify this as an important political task of the locality; it is necessary to accelerate strongly and drastically; mobilize the entire political system to synchronously participate, closely coordinate with relevant departments and branches to focus on reviewing and thoroughly removing existing difficulties and obstacles.

Comrade Tran Nam Hung suggested that some problems with compensation and site clearance should not affect the effectiveness and progress of the entire project; the remaining area should be handed over to Project Management Board 4 (representing the investor) on schedule as required. In particular, it should be noted that the implementation of the policy of not organizing district-level authorities should not affect the effectiveness and progress of compensation and site clearance.

4(1).jpg
The North-South railway intersects National Highway 14E, in Binh Quy commune (Thang Binh). Photo: CONG TU

The leaders of the Provincial People's Committee agreed on the policy to resolve specific cases. For Thang Binh, compensation and support for 2 graves and architectural objects (outside the land acquisition area) belonging to Mr. Dang Ha's household were allowed to facilitate the household in arranging and rebuilding a house on the same plot of land.

1(1).jpg
Provincial leaders directed Thang Binh district to urgently carry out relevant documents and procedures to arrange resettlement for Ms. Nguyen Thi Hong (Binh Dinh commune) in accordance with regulations. Photo: CONG TU

Support for Mrs. Nguyen Thi Thanh's household with 60% of the compensation price for houses and architectural works to remove difficulties, stabilize life and create conditions for the family to hand over the land soon. In the case of Mr. Thai Tan Tao's household, it is agreed to compensate for the land area affected by the project according to the type of agricultural land based on the actual usage status of the family at the time of inspection, ensuring the legitimate rights of the people.

3(1).jpg
A 1.2km long section in Binh Lam commune (Hiep Duc) has been handed over but construction cannot be carried out because there is no access road to the construction site. Photo: CONG TU

For the case in Hiep Duc, it is agreed in principle to assign the District People's Committee to base on the provisions of Decision No. 31, dated October 25, 2024 of the Provincial People's Committee to provide support for stabilizing production for households and individuals whose agricultural land has been recovered in accordance with the regulations as reported and proposed by the district.

In case the conditions for resettlement are not met and the households and individuals within the project's scope of influence do not have any other residential land or houses in the area where the residential land is recovered, the District People's Committee shall consider and arrange resettlement for the above households in the resettlement area according to the approved detailed subdivision plan. On the contrary, the land users must pay 100% of the land use fee for the allocated resettlement land plot in accordance with regulations.

Comrade Tran Nam Hung proposed that the Standing Committee of the District Party Committee: Thang Binh, Hiep Duc strengthen the leadership role, comprehensively direct the compensation and site clearance work in the district; direct the District People's Committee, Party committees, authorities and relevant agencies and units to actively coordinate, organize and synchronously and drastically implement the assigned tasks. Specifically assign the members of the Standing Committee of the District Party Committee and the leaders of the District People's Committee to strengthen propaganda, mobilization, grasp the thoughts and aspirations and dialogue with the people to create high consensus in the implementation process.

[ VIDEO ] - Comrade Tran Nam Hung directed to remove obstacles in land acquisition and clearance in Hiep Duc:

Regularly check and urge progress; promptly direct the handling of difficulties and problems arising, especially cases that are at risk of affecting the progress of site handover. Strive to complete and hand over the entire site through the area before the time of merging provincial administrative units and no longer having district-level government organizations.

Source: https://baoquangnam.vn/tap-trung-xu-ly-dut-diem-vuong-mac-mat-bang-du-an-quoc-lo-14e-3156925.html


Comment (0)

No data
No data

Same tag

Same category

Discover the process of making the most expensive lotus tea in Hanoi
Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City
Village on the mountain top in Yen Bai: Floating clouds, beautiful like a fairyland
Village hidden in the valley in Thanh Hoa attracts tourists to experience

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product