The 3,200 billion project connecting Phap Van Expressway and Ring Road 3 is behind schedule.

The VND3,241 billion project connecting Phap Van - Cau Gie Expressway with Ring Road 3 has only reached 20% progress after more than a year of construction, facing the risk of being delayed due to site clearance problems.

Báo Lâm ĐồngBáo Lâm Đồng06/11/2025

Project overview and strategic role

The project connecting Phap Van - Cau Gie Expressway with Ring Road 3, approved by the Hanoi People's Committee on May 30, 2022, is one of the key infrastructure projects in the south of the capital. The route has a total length of 3.4 km, starting at Tu Hiep commune (Thanh Tri district) and ending at Yen So ward (Hoang Mai district).

Route map connecting Phap Van - Cau Gie Expressway with Ring Road 3.
Route map (red).

With the role of directly connecting two key traffic axes, the project is expected to reduce pressure on existing routes, while opening up space for urban and socio- economic development for the area.

Perspective of intersection and route from above.
The project is considered to be of great significance in completing the traffic infrastructure connection in the southern part of the capital, especially the direct connection with Ring Road 3, the current main traffic axis.

Investment scale and main items

The project is invested by the Hanoi Traffic Construction Investment Project Management Board, with a total capital of up to 3,241 billion VND. Of which, construction costs account for 1,929 billion VND and site clearance costs are 936 billion VND.

To implement, the project needs to recover a total area of ​​316,224 m², including 8,709.2 m² of residential land, 212,613.9 m² of agricultural land and 94,901 m² of public land, corresponding to 2,233 compensation, support and resettlement plans.

An area of ​​agricultural land and public land within the project area.
The total area to be recovered to implement the project is 316,224m² corresponding to 2,233 options, of which residential land is 8,709.2m², agricultural land is 212,613.9m² and public land is 94,901m².

Status of progress and problems in site clearance

Although construction started in July 2023 with a plan to complete by the end of 2025 (760-day schedule), the project is currently seriously behind schedule. According to the Project Management Board representative, the construction volume has only reached about 20%.

Construction site with a huge amount of work remaining.
Currently, the construction volume has only reached about 20%, because the site was handed over "in a haphazard manner", causing contractors to have difficulty in organizing construction.

The main reason was determined to be that the site clearance work was very slow. Out of a total of 2,414 plans, only 881 cases had received compensation. The fact that the site was handed over in an unsynchronized manner, in a "sloppy" manner, caused many difficulties for contractors in organizing continuous construction.

A section of the construction site is temporarily suspended due to land clearance problems.
According to the Hanoi City Traffic Construction Investment Project Management Board, up to now, the project's compensation, support and resettlement work is still very slow.

Specifically, in Hoang Mai district, although land reclamation notices have been issued for 1,331/1,389 cases, the rate of payment and site handover is still low. Similarly, in Thanh Tri district, the approval and payment progress is still facing many obstacles, especially for residential land and office land.

At the intersection with Ring Road 3, the machinery has been withdrawn.
Of the total 2,414 plans, only 881 cases have been paid compensation. The photo shows the intersection with Ring Road 3, where all machinery has been removed.

This situation has left many important sections of the route almost immobile, such as the section through the Big Lagoon or the intersection with the Phap Van - Cau Gie Expressway, where only a few piers have been constructed. In some areas, such as the intersection with Ring Road 3, the machinery has even withdrawn.

The bridge piers are under construction at the intersection with Phap Van - Cau Gie Expressway.
The project started in July 2023, with a progress schedule of 760 days and is scheduled to be completed by the end of 2025. In the photo: The intersection with the Phap Van - Cau Gie Expressway has also just completed construction of a few bridge piers.

With current difficulties, completing the project by the end of 2025 is a big challenge, requiring drastic intervention from authorities to remove the "bottleneck" regarding land clearance.

Source: https://baolamdong.vn/du-an-3200-ty-noi-cao-toc-phap-van-va-va-vanh-dai-3-cham-tien-do-400678.html


Comment (0)

No data
No data

Same tag

Same category

Hero of Labor Thai Huong was directly awarded the Friendship Medal by Russian President Vladimir Putin at the Kremlin.
Lost in the fairy moss forest on the way to conquer Phu Sa Phin
This morning, Quy Nhon beach town is 'dreamy' in the mist
Captivating beauty of Sa Pa in 'cloud hunting' season

Same author

Heritage

Figure

Enterprise

This morning, Quy Nhon beach town is 'dreamy' in the mist

News

Political System

Destination

Product