Lao Cai – Hanoi – Hai Phong railway to start construction this year

On April 26, Prime Minister Pham Minh Chinh - Head of the Steering Committee for key projects and national important projects in the railway sector chaired the online conference of the second meeting of the Steering Committee, connecting with 9 provinces and cities where railway projects pass through. The conference was also attended by Deputy Prime Ministers.

Báo Yên BáiBáo Yên Bái26/04/2025

At Yen Bai bridge, comrade Nguyen The Phuoc - Permanent Vice Chairman of the Provincial People's Committee chaired the Conference; leaders of a number of departments in the province, leaders of the People's Committee of Yen Bai city, Tran Yen district and Van Yen district.
At the conference, delegates heard the leaders of the Ministry of Construction inform about the progress of implementing 24 tasks for ministries, branches and localities to focus on removing difficulties and obstacles, speeding up investment preparation procedures for projects assigned at the first meeting.

Up to now, the Ministry of Construction has completed the draft Resolution on piloting specific and special policies and mechanisms in investment in the construction of railway infrastructure systems and consulted with ministries and branches; submitted to the Government for promulgation of a Resolution implementing Resolution No. 172 of the National Assembly and was approved by the Government in Resolution No. 106; completed the draft Decree detailing a number of articles and measures to implement the Resolutions of the National Assembly on overall technical design, specific and special mechanisms for implementing railway projects.

Local ministries and branches are developing a Decree regulating the temporary use and return of forests to carry out temporary construction works serving the Project; developing a Decree regulating the development of railway science and technology and detailed regulations on research, application, and technology transfer; completing the Railway Industry Development Project, etc.

At the conference, delegates also reported on the progress and made recommendations and proposed solutions to remove difficulties and obstacles in implementing the Lao Cai - Hanoi - Hai Phong railway project; the Hanoi - Lang Son and Hai Phong - Mong Cai railways; the high-speed railway project on the North - South axis; and the Hanoi and Ho Chi Minh City urban railway projects.

Speaking at the conference, Mr. Nguyen The Phuoc - Standing Vice Chairman of the Provincial People's Committee said that the Lao Cai - Hanoi - Hai Phong railway project through Yen Bai province has a length of nearly 77 km, the largest among 9 provinces and cities, and is expected to relocate over 1,000 households. Currently, the province has conducted surveys and measurements at the site, reaching 100% of the volume. Yen Bai Provincial People's Committee will review, integrate and complete land acquisition documents as a basis for implementing project site clearance. Regarding resettlement, Yen Bai province plans to arrange 24 concentrated resettlement areas. Currently, the province is reviewing and finalizing the project list to carry out investment preparation work.

Comrade Nguyen The Phuoc - Standing Vice Chairman of the Provincial People's Committee proposed that the project investor focus on speeding up the progress of preparing the Feasibility Study Report and the site clearance landmark setting dossier as a basis for Yen Bai province to speed up the implementation progress according to the proposed project schedule. At the same time, he requested that the Central agencies issue regulations and guide localities on the order and procedures in implementing the tasks.

In his concluding remarks at the conference, Prime Minister Pham Minh Chinh requested ministries, branches and localities to uphold the spirit of the historic April days 50 years ago, "faster, faster; bolder, more daring" in synchronously implementing railway investment projects; proactively and actively following the resolutions, conclusions and directions of the Central Committee, the Politburo, the National Assembly, the Government and the Prime Minister. In particular, the North-South high-speed railway will start construction in 2026; the Lao Cai - Hanoi - Hai Phong railway will start construction this year. At the same time, continue to deploy urban railways in Hanoi and Ho Chi Minh City.

Regarding capital, the Prime Minister requested to focus on mobilizing central and local capital sources, loan capital, capital from bond issuance, etc. Regarding legal issues, the Prime Minister requested the Ministry of Justice and the Ministry of Construction to complete the draft Resolution on a number of multi-sectoral policies to submit to the Government before April 30 for submission to the National Assembly before May 5; Decrees in the railway sector of the ministries must be completed in May. The Prime Minister also requested localities to focus on site clearance. In particular, the Lao Cai - Hanoi - Hai Phong railway line completed this work in September this year.

Hoai Giang - Tran Tien

Source: https://baoyenbai.com.vn/12/349455/Tuyen-duong-sat-Lao-Cai--Ha-Noi--Hai-Phong-khoi-cong-tr111ng-nam-nay.aspx


Comment (0)

No data
No data

Same category

Enjoy the top fireworks at the opening night of the 2025 Da Nang International Fireworks Festival
Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product