Vietnam.vn - Nền tảng quảng bá Việt Nam

The 870 billion VND Da Lat beltway continuously misses deadlines

TPO - After many years of delays, the Da Lat belt road project in Lam Dong province continues to miss its deadline because 7 households have not yet handed over, causing the construction progress to be delayed.

Báo Tiền PhongBáo Tiền Phong16/09/2025

tp-2.jpg
The Da Lat belt road project ( Lam Dong province) has a length of 7.4km, started construction in July 2021 with a total investment of about 870 billion VND and is expected to be completed in June 2023.
tp-4.jpg
The route runs from Truc Lam - Yen Tu intersection (Xuan Huong ward - Da Lat) to Hoang Van Thu street (Cam Ly ward - Da Lat), using a land fund of more than 27 hectares. The project is invested by the Department of Transport of the former Lam Dong province (now the Department of Construction).
img-8714-2404.jpg
The project is expected to complete infrastructure, enhance traffic connections between urban wards of Da Lat, contribute to reducing traffic congestion in the central area and promote local socio -economic development.
tp-8.jpg
However, according to the Center for Environmental Resources and Land Fund Development of Lam Dong province, 7km of the road has been completed, but the last 400m cannot be constructed because 7 households have not yet handed over the land.
tp-9.jpg
The cause was determined to be that some households still had problems with land documents, resettlement locations, compensation prices, or had complaints related to their rights.
to-9-1442.jpg
For example, Mr. LXS's family is stuck with procedures to adjust the land use right certificate and apply for a construction permit for the remaining area; while Mr. TCT's family requested to be resettled in another area and asked for an additional plot for a 3-generation family.
tp-1.jpg
Faced with the above situation, the Department of Construction of Lam Dong province proposed that the Provincial People's Committee direct the wards to continue allocating resettlement land according to the existing decision; at the same time, promptly approve and publicize resettlement land prices to completely resolve the handover of land.
imgl1357.jpg
An unfinished road makes traffic difficult for people.
tp-imgl1346.jpg
tp-imgl1352.jpg
Heavy rain caused a large amount of rock and soil to spill onto the road, posing a potential risk of accidents.
tp-3.jpg
According to the Center for Environmental Resources and Land Fund Development of Lam Dong province, the compensation, support and resettlement plan of the project was approved by the People's Committee of Lam Dong province with 21 decisions, totaling over 372 billion VND. Of which, over 342 billion VND has been paid to 148 households related to the project.

Source: https://tienphong.vn/tuyen-duong-vanh-dai-da-lat-870-ty-dong-lien-tuc-lo-hen-post1778374.tpo


Comment (0)

No data
No data

Same tag

Same category

Watching the sunrise on Co To Island
Wandering among the clouds of Dalat
The blooming reed fields in Da Nang attract locals and tourists.
'Sa Pa of Thanh land' is hazy in the fog

Same author

Heritage

Figure

Enterprise

The beauty of Lo Lo Chai village in buckwheat flower season

News

Political System

Destination

Product