The Resolution sets out 10 specific task groups for ministries, branches and localities to implement the project of building Ninh Thuan 1 and Ninh Thuan 2 Nuclear Power Plants. Specifically, the Ministry of Industry and Trade will preside over and coordinate with relevant ministries and agencies, Vietnam Electricity Group (EVN), Vietnam National Energy and Industry Group (PVN) to organize negotiations to complete processes and procedures and proceed to sign international treaties with partners on investment cooperation in building the two projects; striving to complete in September 2025 for Ninh Thuan 1 Project and December 2025 for Ninh Thuan 2 Project.
In addition, the Ministry of Finance will preside over negotiations to complete processes and procedures and sign international treaties with partners on providing credit for the two projects; the target is to complete in September 2025 for Ninh Thuan 1 Project and in March 2026 for Ninh Thuan 2 Project.
Regarding project implementation, EVN and PVN will submit a dossier requesting approval of adjustments to the project investment policy for consideration and approval by competent authorities; striving to complete it during the National Assembly session in October and November 2025 for Ninh Thuan 1 Project and no later than May 2026 for Ninh Thuan 2 Project.
After that, the State Appraisal Council (chaired by the Ministry of Finance) will appraise and submit to the Prime Minister for approval the Investment Project and location approval dossier in 2026. Relevant ministries, branches and agencies will appraise and approve the documents; carry out construction and put the project into operation according to the approved feasibility study.
The Government assigned the People's Committee of Khanh Hoa province to make efforts and quickly implement the resettlement and site clearance. Regarding human resource training, the Ministry of Education and Training was assigned to preside over the development and submit to the Prime Minister for approval of the Nuclear Power Human Resource Training Project, which will then be implemented immediately.
The interdisciplinary working group includes representatives of ministries and agencies: National Defense, Public Security, Finance, Government Inspectorate, State Audit... This working group is responsible for supervising the implementation of ensuring the work of preventing and combating corruption, waste and negativity during the implementation of projects.
Source: https://www.sggp.org.vn/chinh-phu-ban-hanh-ke-hoach-trien-khai-du-an-dien-hat-nhan-ninh-thuan-post812033.html