According to information from Vinh Phuc Electricity Company, in recent hot days, the 110kV line pair from Vinh Yen 220kV substation supplying power to Ba Thien, Thang Long, Tam Dao, Thien Ke, Vinh Yen 2 110kV substations has carried 80 - 90% load.
To ensure safe power supply for the areas of Binh Xuyen and Tam Dao districts with many key industrial and tourism loads of the province, it is necessary to synchronously power the above 4 projects. In this situation, the province has directed the Department of Agriculture and Environment to urgently guide the People's Committee of Binh Xuyen district to resolve problems in allocating resettlement land to households and individuals whose land has been recovered to implement power projects in Trung My commune before June 15, 2025.
Complete the appraisal of the adjustment of the land use plan of Binh Xuyen district, including for 2 column foot locations (T03, T04) and 3 road restoration locations (at column foot locations G1.1 (T2); G2.1 (T01); G2.2).
Tam Dao District People's Committee speeds up the approval of land prices to have a basis for establishing and approving compensation and site clearance plans (BT-GPMB) for the remaining 5 pole positions (113, 114, 115, 116, 117 in Hop Chau town) of the 220kV Ba Thien substation project and the 220kV Viet Tri - Tam Duong - Ba Thien line. If necessary, consider using the provisional approval plan to keep up with the construction site handover schedule.
Binh Xuyen District People's Committee urgently completes the BT-GPMB work to hand over the entire pole foot area and route corridor for the investor to implement the construction of the 500kV Vinh Yen substation project and connecting lines.
Speed up the progress of declaration, counting, and approval of the BT-GPMB plan for the 220kV Ba Thien substation project and the 220kV Viet Tri - Tam Duong - Ba Thien line to soon hand over the construction site to the investor. In particular, it is necessary to focus on and prioritize the settlement of positions of columns 148, 149, 150, 481-1 (on these columns there are both 500kV and 220kV lines) and 5 cases of resettlement at the foot of columns 120, 142, 143.
Urgently complete the BT-GPMB work to hand over the construction site for pole positions 3 and 5 of the Ba Thien 220kV Substation Outgoing Project. Direct the People's Committee of Trung My commune to propagate and mobilize households to coordinate and support the Northern Power Project Management Board in gathering materials and soil during the construction of pole position 150 of the 500kV line (combined with 220kV) supplying power to the Vinh Yen 500kV Substation. Request the People's Committee of Binh Xuyen district to complete all of the above work before June 20, 2025.
News and photos: Luu Nhung