Accordingly, for the Trung Nam Urban Area housing construction investment project, the Provincial People's Committee agreed to adjust the progress to December 2024 to complete compensation, site clearance, carry out procedures for land allocation and construction on an area of about 64,416 m²; by June 2025, construction must be completed.
on the above area.
By the end of December 2025, the compensation and site clearance work for the entire project must be completed, procedures for land allocation and construction must be carried out on the remaining area of about 36,722 m²; by June 2026, the entire project must be completed, accepted, handed over and put into operation.
For the housing construction investment project in Urban Area No. 4, the Provincial People's Committee agreed to adjust the progress to the end of March 2025 to complete compensation and site clearance for the remaining area to continue construction.
By the end of December 2025, the project must be completed, accepted and handed over to put into operation.
The Provincial People's Committee requested the investors of the two projects, Tam Nhat Nam Investment Joint Stock Company and Quang Nam Transport Joint Stock Company, to be responsible for working with the People's Committee of Dien Ban town to review and evaluate the ability to carry out compensation and site clearance for the remaining area.
Urgently implement the next procedures of the project to ensure compliance with legal regulations on construction, housing, real estate business and other relevant laws; take full responsibility before the law for any violations in project investment, construction and real estate business at the project.
Prepare detailed project progress (including compensation and site clearance progress; project investment and construction progress and capital allocation plan) and send it to the Department of Planning and Investment, Department of Construction, Department of Natural Resources and Environment, and Dien Ban Town People's Committee as a basis for progress management and monitoring of project implementation.
judgment as prescribed.
The Provincial People's Committee also assigned the People's Committee of Dien Ban town to urgently direct relevant departments, units and localities to coordinate with investors to focus on speeding up progress and resolving difficulties in the project.
Compensation and site clearance work and urging investors to speed up construction progress to ensure compliance with approved planning and ensure progress time adjusted by the Provincial People's Committee, promoting project efficiency and objectives.
In case the compensation and site clearance work for the remaining area is not completed by the deadline; coordinate with the investor to review and evaluate the ability to carry out compensation and site clearance work, and propose to the Provincial People's Committee a handling direction based on Plan No. 1892 dated March 19, 2024 of the Provincial People's Committee to complete the project.