Nhon Trach Bridge to be exploited in phases, waiting for synchronization of the entire Ring Road 3 route

(PLVN) - Due to the first two sections not being completed, Nhon Trach Bridge, the largest bridge on Ho Chi Minh City's Ring Road 3, will be exploited in two phases, starting from August 2025 with an urban road scale.

Báo Pháp Luật Việt NamBáo Pháp Luật Việt Nam23/06/2025

According to the traffic organization plan recently submitted to the Ministry of Construction by the My Thuan Project Management Board, the investor, Nhon Trach Bridge will be temporarily operated as an urban road in the first phase (from August 2025 to December 2026), and will only be put into operation according to expressway standards after other connecting sections are completed.

Nhon Trach Bridge has a total length of more than 8.2 km, spanning the Dong Nai River, belonging to the Component Project 1A, Tan Van - Nhon Trach section, using Korean ODA loan (EDCF) and domestic counterpart capital. Currently, the project has reached more than 95% of the volume and is expected to be completed in June 2025.

Cầu Nhơn Trạch sẽ được khai thác theo hai giai đoạn, bắt đầu từ tháng 8/2025

Nhon Trach Bridge will be exploited in two phases, starting from August 2025.

The two phases of operation are divided specifically. Phase 1 (from August 2025 to December 2026): In the first phase, Nhon Trach Bridge and the access road will be operated as an urban route, allowing the circulation of both cars and two- and three-wheeled vehicles depending on each section. On the Dong Nai side, traffic will be organized with one lane for cars and one mixed lane, running from DT.25B road to Ly Tu Trong road, motorbikes are not allowed to circulate on Nhon Trach Bridge.

From Ho Chi Minh City, arrangements will be made for cars to move from Nhon Trach Bridge, turn around through connecting branches before entering the Ho Chi Minh City - Long Thanh - Dau Giay Expressway. Container trucks and trailers are temporarily not allowed to travel across the bridge because the turning points do not meet technical requirements.

Phase 2 (after December 2026), when the connecting sections are completed, the entire route will be operated according to expressway standards. Nhon Trach Bridge in particular will organize traffic with two lanes for motor vehicles and two mixed lanes, with a clear divider between the lanes to ensure safety for vehicles.

Ho Chi Minh City Ring Road 3 is a national key project, passing through 4 provinces and cities including Ho Chi Minh City, Binh Duong, Dong Nai and Long An with a total length of more than 90 km. To date, the 15.3 km section through Binh Duong has been completed. Together with Component Project 1A (Nhon Trach Bridge), the remaining 76 km is being implemented with a total capital of nearly 75,400 billion VND.

It is expected that the entire Ring Road 3 route will be completed in 2026, opening up a traffic axis connecting Ho Chi Minh City and the provinces of the Southern Key Economic Zone, contributing to promoting socio-economic development and relieving existing urban traffic pressure.

Source: https://baophapluat.vn/khai-thac-cau-nhon-trach-theo-giai-doan-cho-dong-bo-toan-tuyen-vanh-dai-3-post552668.html


Comment (0)

No data
No data

Same tag

Same category

Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition
Mu Cang Chai traffic jam until evening, tourists flock to hunt for ripe rice season

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product