Urgently change the purpose of forest use to serve Tan Phu - Lien Khuong expressway

On the morning of October 15, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai chaired a meeting with leaders of the Department of Agriculture and Environment, Project Management Board No. 1 and other departments, branches and sectors on issues related to the conversion of forest and forest land use purposes for the two expressway projects Tan Phu - Bao Loc and Bao Loc - Lien Khuong.

Báo Lâm ĐồngBáo Lâm Đồng15/10/2025

quan-cnah.jpg
Member of the Provincial Party Committee, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai chaired the meeting.

The meeting focused on speeding up progress, completing procedures and assigning responsibilities in changing the purpose of using forests and forest land, and handing over the land for these two expressways.

Deputy Director of the Department of Agriculture and Environment spoke and discussed instructions on implementation procedures and processes.
Deputy Director of the Department of Agriculture and Environment spoke and discussed instructions on implementation procedures and processes.

The two expressway projects Tan Phu - Bao Loc and Bao Loc - Lien Khuong are component projects of the Dau Giay - Lien Khuong expressway, with a total length of more than 200 km.

nghi8240.jpg
Leaders of forest owners and Land Fund Development Center attended the meeting.

The Tan Phu - Bao Loc Expressway project has a route passing through 104 hectares of production forest. The conversion of forest use purposes is necessary to develop key transport infrastructure, connect the Southeast region with the Central Highlands, promote regional connectivity, attract investment, develop tourism, logistics, high-tech agriculture, improve people's lives and create momentum for socio -economic development of the locality and region.

nghi8239.jpg
Vice Chairman of the Provincial People's Committee Nguyen Hong Hai requested departments, branches and units to uphold their sense of responsibility.

In his speech, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai requested departments, branches and units to uphold the spirit of responsibility, urgency and shared responsibility to quickly complete tasks and speed up the progress of forest conversion.

He also agreed to assign two forest owners, Da Huoai and Da Teh Forestry Company, to carry out the task of preparing forest exploitation records and requested the Department of Agriculture and Environment to guide the procedures related to forest land transfer for the two expressways.

nghi8243.jpg
Leaders of Departments and Land Registration Office attended the meeting.

Regarding the content of forest land transfer, forest exploitation plan, forest product exploitation, forest compensation, he also requested the Department of Agriculture and Environment to guide forest owners to implement and urge units to effectively implement assigned tasks.

nghi8242.jpg
Representatives of the Provincial People's Committee, Department of Construction and Construction Investment Project Management Board No. 1 attended the meeting.

The comrade assigned the Department of Finance to advise on advance payment for replacement forest planting, guide the arrangement of funds for the two forest owners to develop a forest exploitation plan and assigned the Department of Construction to be responsible for urging the completion of stake planting and handing over of land acquisition and clearance markers, to be completed by October 20, 2025.

This is the expressway that Lam Dong people have been waiting for and expecting for many years. With the highest spirit, together with the community responsibility, the departments, branches and units are implementing step by step, urgently and as quickly as possible to hand over the site to the investor.

Vice Chairman of the Provincial People's Committee Nguyen Hong Hai

The Tan Phu - Bao Loc Expressway project is expected to start construction on December 19, 2025. The Bao Loc - Lien Khuong section started construction at the end of June 2025. However, due to the incomplete handover of the clean site, the investor has not yet organized construction.

Source: https://baolamdong.vn/khan-truong-chuyen-muc-dich-su-dung-rung-phuc-vu-cao-toc-tan-phu-lien-khuong-395788.html


Comment (0)

No data
No data

Same tag

Same category

In the season of 'hunting' for reed grass in Binh Lieu
In the middle of Can Gio mangrove forest
Quang Ngai fishermen pocket millions of dong every day after hitting the jackpot with shrimp
Yen Nhi's national costume performance video has the highest views at Miss Grand International

Same author

Heritage

Figure

Enterprise

Hoang Thuy Linh brings the hit song with hundreds of millions of views to the world festival stage

News

Political System

Destination

Product