Also participating were representatives of relevant departments, branches, Cho Moi District People's Committee, Bac Kan City Land Fund Development Center and Project Management Board 2 (Ministry of Construction).
The inspection aims to review the progress of implementation in accordance with the timelines previously concluded in Notice No. 68/TB-UBND dated April 11, 2025. Accordingly, many priority sections for land acquisition and construction of bridges through Thanh Thinh and Nong Ha communes have basically completed procedures to proceed with compensation payments to people and hand over the site in April and early May 2025, such as the locations serving the construction of Ban Chang bridge, Na Deo bridge and Na Ban bridge.
At the meeting, the provincial leaders agreed with the proposal of Project Management Board 2 on the implementation of a service road across the Cau River. This route will facilitate the transportation of sand, rock, and soil from the staging area to the construction site, contributing to speeding up the progress of the entire route.

Provincial leaders requested relevant units to urgently coordinate, thoroughly resolve existing problems and complete work according to progress commitments.
During the program, the delegation grasped the situation of material supply for the construction of this project at the quarry and artificial sand production line of Hong Ha Joint Stock Company in Xuat Hoa ward (Bac Kan city)./.
Source: https://baobackan.vn/kiem-tra-tien-do-giai-phong-mat-bang-cao-toc-cho-moi-bac-kan-post70456.html