Nhon Trach 3 Power Plant, the first LNG power plant in Vietnam, is completing preparations to be ready for operation in the near future. |
By the end of April 2025, most of PetroVietnam 's key production targets had been achieved and exceeded the plan by 3.8% to 19.5%. Specifically, crude oil production reached 3.16 million tons, exceeding the 4-month plan by 12.8%; Gas production reached 1.98 billion m³, exceeding 10.4%; Electricity production reached 11.06 billion kWh, exceeding 9.9%; Gasoline production reached 5.39 million tons, exceeding 12.7%; NPK fertilizer production reached 187.3 thousand tons, exceeding 19.5%.
Notably, the Dai Hung mine development project phase 3 was completed 20 days ahead of schedule, contributing to increasing output and supplying raw materials for electricity production during the current hot season.
Nhat Minh
Source: https://baobariavungtau.com.vn/kinh-te/202505/nhieu-chi-tieu-san-xuat-chinh-cua-petrovietnam-vuot-ke-hoach-1043281/