Construction continues during September 2nd holiday to ensure progress of Rach Mieu 2 bridge

Việt NamViệt Nam06/09/2024


A representative of the My Thuan Project Management Board said that the unit arranged over 450 workers and technical staff to work during the September 2 holiday to ensure project progress and soon complete the Rach Mieu 2 Bridge (connecting Tien Giang and Ben Tre provinces) as planned.

ANH 2- BEN TRE - TR 8.jpg
Technical staff and workers increased to 3 shifts and 4 shifts to ensure the progress of Rach Mieu 2 bridge project.

Accordingly, at the construction site of the Rach Mieu 2 Bridge investment project, there are 32 construction teams, with 147 construction equipment and 80 technical staff. As of the end of August 2024, the Rach Mieu 2 Bridge project has been completed 57.73%, basically meeting the planned progress. According to the leader of the My Thuan Project Management Board, the units seriously implemented the construction "3 shifts, 4 teams", determined to complete the project as directed by the Prime Minister and the Minister of Transport , striving to complete the project on the occasion of the National Day celebration on September 2, 2025.

PHAN HUY

Source: https://www.sggp.org.vn/thi-cong-xuyen-le-2-9-de-dam-bao-tien-do-cau-rach-mieu-2-post757308.html


Comment (0)

No data
No data

Same tag

Same category

Admire the unique pagoda made from more than 30 tons of ceramic pieces in Ho Chi Minh City
Village on the mountain top in Yen Bai: Floating clouds, beautiful like a fairyland
Village hidden in the valley in Thanh Hoa attracts tourists to experience
Ho Chi Minh City cuisine tells stories of the streets

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product