Attending the conference were comrades: Le Thi Kim Dung, Standing Deputy Secretary of the Provincial Party Committee; Nguyen Van Son, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council; Phan Huy Ngoc, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Nguyen Manh Tuan, Member of the Standing Committee of the Provincial Party Committee, Standing Vice Chairman of the Provincial People's Committee; Van Dinh Thao, Member of the Standing Committee of the Provincial Party Committee, Director of the Department of Finance; leaders of a number of departments, branches, and provincial investment project management boards; representatives of contractors and leaders of a number of communes.
Delegates at the meeting. |
Focus on removing obstacles immediately
Tuyen Quang - Ha Giang Expressway Project (Phase 1), the section through the old Tuyen Quang province has a total route length of 77km. Up to now, regarding compensation and site clearance, 99.98% of the site has been handed over to the contractor to ensure the route is open. However, there are still 66 The household has not yet handed over the site to the contractor. The project has 07 construction packages that have been implemented, reaching 41% of the contract value.
Provincial Party Secretary Hau A Lenh chaired the meeting. |
For the Tuyen Quang - Ha Giang Expressway Project (Phase 1), the section through the old Ha Giang province has a total The project length is 27,480km. Up to now, 100% of the compensation and site clearance work has been completed. Currently, contractors are organizing construction, with a total of 692 personnel present at the site; 342 construction machinery and equipment; and the output to date has reached 65% of the contract value.
Regarding the My Lam Urban Resort Project, the investor is Thai Son Construction Investment Joint Stock Company, investing on an area of over 540 hectares; total investment: 17,113 billion VND. Currently, the compensation and site clearance work is slow, reaching only 24.6%...
At the conference, delegates focused on analyzing subjective and objective causes of slow project implementation progress and proposed solutions and solutions to remove difficulties and obstacles to speed up the progress of the Tuyen Quang - Ha Giang Expressway Project (phase 1), the section through the old Tuyen Quang province and the My Lam Resort Urban Area Project.
Permanent Vice Chairman of the Provincial People's Committee Nguyen Manh Tuan reported on the progress of key projects at the meeting. |
Accordingly, the main cause of the delay is determined to be the slow site clearance, along with the shortage and high cost of common construction materials such as sand and stone. It is requested that the provincial departments, branches and wards and communes with any problems resolve the compensation issue and promptly hand over the site to the construction unit...
Unite for the development of Tuyen Quang
Concluding the conference, Provincial Party Secretary Hau A Lenh emphasized: The functional departments, branches, provincial management boards, contractors and construction units need to clearly identify: Tuyen Quang - Ha Giang Expressway Project (phase 1) and My Lam Resort Urban Area are two key projects of the province.
Contractor representative speaking at the meeting. |
These are projects that are both politically significant and contribute significantly to the socio-economic development of the province. Therefore, the entire political system at all levels, sectors, contractors and construction units must resolutely take part and coordinate to remove bottlenecks and obstacles.
He requested the Provincial Party Committee to direct departments, branches and localities to direct communes and wards in the project area to develop plans for site clearance, solve infrastructure issues, make detailed plans, assign clear tasks and responsibilities, and evaluate progress daily and weekly. At the same time, review all administrative procedure problems managed by the provincial departments and branches to remove bottlenecks.
Provincial Party Secretary Hau A Lenh also requested departments and branches to establish a coordination mechanism to discuss and resolve difficulties and obstacles in legal procedures, creating the most favorable conditions for contractors and construction units to speed up the implementation progress. The Provincial Party Committee and People's Committee should study and establish a Steering Committee for key projects of the province to have centralized leadership, promptly speed up the progress of major projects on time and ahead of schedule.
The Provincial People's Committee needs to promptly direct departments, branches and sectors to focus on solving the issue of compensation, site clearance and controlling the price of basic construction materials; grasp the thoughts and aspirations of the people and directly mobilize and resolve those thoughts and aspirations in accordance with the provisions of law.
The project implementing enterprise raised some difficulties in project implementation. |
The Investment and Construction Project Management Boards focus on human resources and complete the project implementation documents: Tuyen Quang - Ha Giang Expressway (phase 2) associated with the connection of the traffic network planning and the socio-economic development plans of the province. When developing urban infrastructure, it must be associated with the planning and energy use plan to meet the development of the province...
The Provincial Party Secretary requested that contractors who have any problems during the implementation process should promptly report to the province for resolution. The Provincial Party Secretary requested that everyone must work together for the development of Tuyen Quang province, using these two important key projects to gain experience for other projects.
Ngoc Hung