This move shows that Ca Mau is determined to strictly handle investors and contractors who do not carry out projects on schedule as committed to ensure the disbursement target of 100% of public investment capital allocated by the Government to the province in 2025.

Ca Mau is determined to strictly handle investors and contractors who do not carry out projects on schedule as committed.
Overcome the sun, overcome the rain…
At the project to invest in building the embankment along the Bac Lieu river, implemented by the Management Board of the Project for Investment in Construction of Agricultural and Rural Development Works of Ca Mau province (management board), despite the unusual stormy weather and rising river water levels affecting the construction progress of the works and projects, despite the rain, storms and storms day and night, the workers were always present at the construction site to do their jobs well, not letting the project slow down.
Director of the Management Board Nguyen Minh Duc said that in 2025, the Board was allocated 1,080 billion VND to carry out projects of the agricultural and environmental sectors including: dikes, embankments, culverts, canal dredging...
“By the end of October 2025, the industry's public investment capital had disbursed 60.4%. Although there are only 2 months left, we will carry out the project's progress in an "accelerated" manner, working day and night, without interruption. Any construction unit that is negligent in not fulfilling its commitment, we will take appropriate measures and will not allow the project to continue construction...", Mr. Duc informed.
According to Mr. Luong Quy Thai - Deputy Director of the Bac Lieu Traffic Construction Investment Project Management Board, the total capital recorded in 2025 in Bac Lieu province was previously 1,540 billion VND, implementing 9 projects. Of which, 3 transitional projects include: Ninh Quoi - Ngan Dua, Phuoc Long - Ba Dinh, Pho Sinh - Canh Den traffic routes. 3 new projects starting construction include: the inner ring road, the outer ring road of Bac Lieu city (phase 1), Hoa Binh 2 bridge and the road connecting to Giong Nhan - Ganh Hao road. 3 projects preparing for investment include: Vam Xang 2 bridge, Bac Lieu 5 bridge, the coastal road through Bac Lieu province previously and the branch connecting to Nam Song Hau.

The Provincial People's Committee is ready to quickly resolve the issue with the spirit of "what is difficult is for the government, what is easy is for businesses".
"As of October 2025, the Board has disbursed more than 307 billion VND (reaching 19.9%), currently the undisbursed public investment capital is 1,233 billion VND. With the remaining capital being too large and the time being too short, it is impossible to disburse 100% as required by the province," said Mr. Luong Quy Thai.
Identify “bottlenecks”
Explaining the reason why the public investment capital for Bac Lieu traffic projects in 2025 was not disbursed, Mr. Luong Quy Thai said that currently, in the 3 groups of traffic projects, there are 2 problems: one is the institutional stage, the other is site clearance.
"The three transitional projects all have technical problems during construction. On the Ninh Quoi - Ngan Dua route, there is a problem with the clearance of 4 trees. It has been 10 years but it has not been resolved yet," said Mr. Thai.

Up to now, all the difficulties facing public investment projects in Ca Mau province in 2025 can be said to have been identified as the "bottleneck of bottlenecks" leading to slow disbursement progress.
Along with that, some projects are stuck with site clearance work such as: land acquisition, compensation, resettlement support to implement investment in construction of the expressway from the former Ca Mau City to Dat Mui; storm shelter and Cai Cung fishing port; investment in upgrading and expanding the U Minh - Khanh Hoi route; investment in construction of resettlement area in hamlet 6B, Song Doc...
Up to now, all the difficulties facing Ca Mau province's public investment projects in 2025 can be said to have been identified as the "bottleneck of bottlenecks" leading to slow disbursement progress. The most important thing is that the remaining implementation volume and capital plan to be disbursed in the fourth quarter is very large (over 7,630 billion VND, an average of 2,544 billion VND must be disbursed per month).
Source: https://doanhnghiepvn.vn/doanh-nghiep/ca-mau-giai-ngan-von-dau-tu-cong-co-kip-ve-dich/20251030112015707