The Ministry of Transport has just issued a document requesting the People's Committee of Cao Bang province and the Cao Bang Department of Transport to speed up the implementation of the Cao Bang city bypass project.
Construction of Cao Bang City bypass.
The document clearly states that the Cao Bang City bypass project was assigned by the Ministry of Transport to the Cao Bang Department of Transport as the investor, and the site clearance sub-project was implemented by the Cao Bang Provincial People's Committee.
The project started in January 2023 and is scheduled to be completed in June 2024. To resolve land issues, the Ministry of Transport has issued many documents requesting local authorities and relevant agencies to coordinate and hand over the land on schedule.
However, according to the investor's report, up to now, the project still has 1/7.04 km of land that has not been handed over, and the implementation volume has only reached 53%.
"In the past 6 months, site clearance and construction progress have not progressed, and the project has not been completed on schedule," said the Ministry of Transport.
To speed up the implementation progress, the Ministry of Transport requested the People's Committee of Cao Bang province to direct relevant agencies to urgently complete compensation work and hand over the entire remaining site of the project (at sections Km 3+250 - Km 3+850, Km 4+850 - Km 4+950, Km 7+250 - Km 7+558) to the construction unit in September 2024.
"Cao Bang Department of Transport must closely coordinate with local agencies to find solutions to speed up site clearance work.
The project management board, contractors, and supervision consultants also need to review the remaining workload, establish a detailed construction schedule, determine the completion time of the remaining items (foundation, foundation, road surface, etc.); mobilize sufficient human resources, equipment, supplies, materials, organize scientific construction, and complete the project within the required deadline," the Ministry of Transport requested.
The Cao Bang City bypass construction investment project has a total route length of about 7.5km. The starting point of the project is at Km 0+00 intersecting with National Highway 34B (at Km 53+250) in Duyet Trung Ward, Cao Bang City. The end point is at Km 7+558.18 intersecting with National Highway 3 (at Km 271+500) in Song Hien Ward, Cao Bang City.
The project was approved for investment according to the scale of a grade III mountainous road, including 2 lanes, a 12m wide roadbed, and a design speed of 60km/h. Particularly, the section from the intersection of Vo Nguyen Giap Street to the end of the route has a 23m wide roadbed. The total investment of the project is nearly 222 billion VND.
Source: https://www.baogiaothong.vn/cham-giai-phong-mat-bang-du-an-tuyen-tranh-tp-cao-bang-chua-the-ve-dich-192240918193046775.htm