Approval of investment policy for Quang Son 1 Industrial Park

Comrade Nguyen Thanh Binh, Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee, has just signed a decision approving the investment policy and investor for the Quang Son 1 Industrial Cluster Infrastructure Business Investment Project (Area A), in Dong Hy district.

Báo Thái NguyênBáo Thái Nguyên23/05/2025

The investor of Quang Son 1 Industrial Cluster (Area A) is CACO3 Quang Son Trading and Production Joint Stock Company, headquartered in Thong Nhat hamlet, Quang Son commune, Dong Hy district. Photo: TL
The investor of Quang Son 1 Industrial Cluster (Area A) is CACO3 Quang Son Trading and Production Joint Stock Company, headquartered in Thong Nhat hamlet, Quang Son commune, Dong Hy district. Photo: TL

The investor of the above Industrial Cluster (IC) is CACO3 Quang Son Trading and Production Joint Stock Company, headquartered in Thong Nhat Hamlet, Quang Son Commune. The project's objective is to invest in the construction and business of the technical infrastructure of the IC; to trade in real estate, land use rights owned by the owner, user or lessee; to lease warehouses, factories, and places to store goods.

Quang Son 1 Industrial Cluster (Area A) has a usable area of ​​15.3 hectares, including the following items: Operation and service area; industrial production area, warehouse, regulating lake, internal traffic, green tree system. The project implementation location is in Tan Long and Quang Son communes (Dong Hy).

The total investment capital of the CCN is over 75 billion VND, of which the investor's capital accounts for 20%, the rest is borrowed capital from credit institutions. The project's operating period is 50 years according to the decision to establish the CCN. The progress of basic construction and putting the project into operation will start from the fourth quarter of 2025.

The People's Committee of Thai Nguyen province assigned departments, branches and local authorities to coordinate and support investors during the implementation process, while strengthening inspection and supervision to ensure the progress and quality of the project. The People's Committee also requested CACO3 Quang Son Trading and Production Joint Stock Company to properly fulfill its commitments according to the implementation schedule in the investment policy approval.

Source: https://baothainguyen.vn/kinh-te/202505/chap-thuan-chu-truong-dau-tu-cum-cong-nghiep-quang-son-1-b9e21f6/