The Chairman of Lao Cai Provincial People's Committee has just signed Decision No. 2051/QD-UBND approving the adjustment of Component Project 2 to build an Airport under the Sa Pa Airport Construction Investment Project, Lao Cai Province under the public-private partnership (PPP) method.
Accordingly, the People's Committee of Lao Cai province decided to maintain the approved scope and scale of investment in phase 1; including the construction of Sa Pa Airport (Cam Con commune, Bao Yen district, Lao Cai province) meeting the standards of a level 4C airport (according to the classification of the International Civil Aviation Organization ICAO) with a capacity of 1.5 million passengers/year and a level II military airport.
However, the Sa Pa Airport Project has added the content of completing the items of phase 2 to reach the capacity of 3 million passengers/year to ensure compliance with the planning, including: Completing the construction of 2 taxiways connecting terminal 14, adding a parallel taxiway connecting terminal 14 to the aircraft parking lot, taxiway width 23 m; constructing 3 additional parking positions for Code C aircraft and equivalent; expanding the passenger terminal to reach the capacity of 3 million passengers/year (two phases); arranging telescopic bridges to pick up and drop off passengers...
Total investment for Component Project 2 is nearly VND 6,394 billion (including VAT); Phase 1 is over VND 3,982 billion; Phase 2 is nearly VND 2,412 billion.
Of which, equity and loan capital are nearly VND 3,538 billion; State capital is nearly VND 2,856 billion (accounting for 44.38% of total investment). The project has an investor selection method of domestic open bidding, without pre-selection. The expected time for investor selection is from the third quarter of 2025.
According to the decision of the Lao Cai Provincial People's Committee, the implementation period of the Sa Pa airport project under the PPP method and BOT contract is 46 years and 7 months. Of which, the operation, exploitation and capital recovery period is 43 years and 6 months. Phase 2 is implemented during the operation and exploitation period without affecting the project's financial plan.
At the same time, the People's Committee of Lao Cai province assigned the inviting party (Department of Construction) to take the lead and coordinate with relevant agencies to complete the bidding documents, submit them to competent authorities for consideration and approval as a basis for selecting investors and organizing the selection of investors in accordance with the provisions of law.
Previously, Deputy Prime Minister Le Van Thanh signed Decision No. 1773/QD-TTg dated October 21, 2021 on the investment policy for the Sa Pa Airport Construction Investment Project, Lao Cai province under the public-private partnership (PPP) form.
In December 2024, Deputy Prime Minister Tran Hong Ha signed Decision No. 1621/QD-TTg on adjusting the investment policy of the Sa Pa Airport construction investment project in Lao Cai province under the PPP method, which was previously approved by the Prime Minister in Decision No. 1773/QD-TTg.
Accordingly, the Sa Pa Airport Project will be implemented on a 371-hectare land plot in Cam Con Commune, Bao Yen District, Lao Cai Province. The objective of the Sa Pa Airport construction investment project is to meet the increasing demand for air transport, contributing to promoting socio-economic development. At the same time, it ensures high mobility in defense, as well as in rescue and relief work; ensures national defense and security of the Northwest region and Lao Cai Province; in line with the planning and orientation of transport development.
(According to VnEconomy)