Site clearance work reached over 94%
The working group inspected the field in Hiep Thanh and Phu Hoi communes, where functional units are organizing on-site measurement and counting. Vice Chairman of the Provincial People's Committee Nguyen Hong Hai encouraged households that had to relocate to serve the project, and discussed with the village Party Secretary and people about the work of counting, measuring and compensation.

Through the discussion, people expressed their cooperation and wished to soon receive compensation to hand over the site for the construction of the expressway.


The two expressway projects Tan Phu - Bao Loc and Bao Loc - Lien Khuong pass through 15 communes and wards. The work of counting crops and structures has been basically completed, reaching over 94%. There are still some households that have not been counted because the land users are outside the province, so contacting them to carry out the counting is difficult.
After the field inspection, comrade Nguyen Hong Hai chaired a working session at the People's Committee of Duc Trong commune to listen to the leaders of the People's Committees of communes and wards; relevant departments, units and the Investment Project Management Board of the areas report on the implementation of site clearance and construction of resettlement areas to serve the Tan Phu - Bao Loc and Bao Loc - Lien Khuong expressway projects.

At the meeting, local representatives raised a number of difficulties and problems such as large land plot fluctuation rates, actual boundaries being different from cadastral maps, and complex terrain making it difficult to move for inventory.
The Provincial Land Fund Development Center proposed that the Department of Agriculture and Environment direct the Provincial Land Registration Office to support map correction to ensure the progress of the inventory, committing to complete the inventory work by November 5 at the latest.
Speed up the implementation of resettlement areas
According to the report at the meeting, the construction of resettlement areas is facing difficulties due to land acquisition, bad weather and material supply issues. However, the localities and relevant units are actively coordinating to resolve and intensify construction to ensure progress.

Vice Chairman of the Provincial People's Committee Nguyen Hong Hai requested departments, branches, sectors and localities to continue to coordinate closely, focus on resolving difficulties to speed up the implementation of resettlement areas, ensure the rights of people and the progress of key expressway projects.

Vice Chairman of the Provincial People's Committee Nguyen Hong Hai requested the investor to complete the selection of construction contractors for the Bao Loc - Lien Khuong project in December 2025 to soon start construction. Lam Dong Provincial People's Committee is focusing on directing, resolutely removing obstacles, speeding up the progress of site clearance, creating favorable conditions for the handover of land and construction of the expressway project.

Comrade Nguyen Hong Hai emphasized that the province is under great pressure to disburse 7,500 billion VND for two expressway projects, so it is necessary to implement synchronously, closely and flexibly in the spirit of "doing easy first, difficult later" to speed up public investment progress.
In that spirit, the Vice Chairman of the Provincial People's Committee requested the relevant authorities to urgently complete the legal documents related to the site clearance work, post the documents in early November 2025; at the same time, ensure the inventory and resettlement process is transparent, impartial and in accordance with the law.
These are two expressway projects that are urgently needed by the people. The government is giving strong direction, requiring departments and branches to be more proactive, to uphold their sense of responsibility and to achieve concrete results soon.
Vice Chairman of the Provincial People's Committee Nguyen Hong Hai
Source: https://baolamdong.vn/pho-chu-tich-ubnd-tinh-lam-dong-nguyen-hong-hai-kiem-tra-tien-do-gpmb-cac-du-an-cao-toc-tan-phu-bao-loc-va-bao-loc-lien-khuong-399180.html