Quang Ngai speeds up progress of 3,500 billion VND traffic project

After nearly 2 years of construction, the Hoang Sa - Doc Soi road project has only completed 27% of its volume due to land clearance problems. The leaders of the Quang Ngai Provincial People's Committee requested synchronous implementation of solutions to clear the obstacles and speed up the progress.

Báo Đầu tưBáo Đầu tư29/12/2024

Hoang Sa - Doc Soi road project has a total investment capital of 3,500 billion VND.

The Hoang Sa - Doc Soi Road project has a total investment of 3,500 billion VND, started at the end of 2023, expected to be completed in 2027, invested by the Quang Ngai Provincial Traffic Construction Investment Project Management Agency.

The project has a route length of 26.88 km, with a total planned construction area of ​​more than 172 hectares, passing through 6 eastern communes of Quang Ngai.

Up to now, the project has been handed over a clean site of more than 71 hectares, equivalent to more than 41%. However, it is not continuous, there is no road, the contractor has difficulty in accessing and organizing construction.

Currently, only 7/9 bridges have been constructed; 1/25.4 km of roadbed; 26/156 cross-culverts have been constructed. The cumulative value of completed construction to date is 642/2,382 billion VND, reaching 27% of the construction value according to the contract.

Vice Chairman of Quang Ngai Province Nguyen Cong Hoang said that in order for the project to follow the set schedule, relevant parties need to actively coordinate to effectively resolve problems in compensation and site clearance.

The Vice Chairman of the Provincial People's Committee requested that communes and wards where the project passes must base on reality and establish many teams to handle problems in site clearance. The implementation motto is to have clear people, clear work, clear time, clear results, determined to speed up the progress of handing over the project site to the contractor, and timely disbursement volume.

In addition, the Vice Chairman of the People's Committee of Quang Ngai province requested units to focus on implementing synchronous solutions to clear obstacles, promptly hand over clean sites so that contractors can work overtime, increase construction shifts, compensate for delayed workloads, speed up project progress, and disburse all allocated capital, with priority given to central capital.

Source: https://baodautu.vn/quang-ngai-thuc-tien-do-du-an-giao-thong-3500-ty-dong-d430122.html


Comment (0)

No data
No data

Same tag

Same category

'Sa Pa of Thanh land' is hazy in the fog
The beauty of Lo Lo Chai village in buckwheat flower season
Wind-dried persimmons - the sweetness of autumn
A "rich people's coffee shop" in an alley in Hanoi, sells 750,000 VND/cup

Same author

Heritage

Figure

Enterprise

Wild sunflowers dye the mountain town yellow, Da Lat in the most beautiful season of the year

News

Political System

Destination

Product