To ensure construction progress, the contractor mobilized nearly 100 workers and more than 30 vehicles and machines to deploy 3 construction teams simultaneously at the construction site.
The project is implemented in Ha Loc commune and Phu Ho commune ( Phu Tho town) with a recovered land area of 3.31 hectares; the number of affected households is expected to be 188 households.
Up to now, in Ha Loc commune (3.2ha): Inventory of land, crops, trees and structures on land has been conducted for 149/166 households, of which compensation plans have been approved for 76 households with a recovered area of 10,034.5m2, with a total amount of 3.385 billion VND.
Installing rib reinforcement, serving the construction of the underpass at km1+767
In Phu Ho commune (0.11ha): Conducted inventory of land, crops, trees and structures on land for 16/22 households, and approved compensation for 16 households with a recovered area of 400.7m2, the amount of money is 997 million VND.
Along with focusing on site clearance, construction work is also being carried out vigorously and urgently. Tu Lap Construction Company Limited has mobilized nearly 100 engineers, workers and more than 30 specialized vehicles and machines to deploy into 3 construction teams at the construction site. As of May 29, the completed construction volume reached 27,102/467,731 billion VND, focusing on works such as: excavation, bamboo pile driving, underpass, precast structures...