Lack of sand, Chau Doc - Can Tho - Soc Trang expressway through Can Tho area facing difficulties

Sand material sources are not guaranteed in terms of volume and mining capacity, some sand mines have a large amount of mud so mining is ineffective. This is a bottleneck in the progress of the Project.

Báo Đầu tưBáo Đầu tư29/12/2024

According to the Department of Construction of Can Tho City, the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1, Component Project 2, Component Project 3, Component Project 4, the section passing through Can Tho City has a total area of ​​about 816.64 hectares that must be cleared for the entire route.

Up to now, 3,641 households have handed over their land, reaching 100%. The investor has received 816.64 hectares from localities, reaching 100% of the area.

Regarding construction work, the Project has a total of 11 construction packages (10 construction packages and 1 traffic safety system construction package). The total value of the 10 main construction packages and 1 traffic safety system construction package is 8,748/19,902 billion VND, reaching 43.96%.

Regarding disbursement, from the commencement of construction to the reporting time, the Project has disbursed 13,143/18,640 billion VND, reaching 70.51%.

The disbursement in 2025 alone as of the reporting date is 1,885/7,286 billion VND, reaching 25.87% of the allocated capital plan. The investor strives to disburse 100% of the assigned capital plan.

Construction of an overpass on the Chau Doc - Can Tho - Soc Trang expressway.

As planned, the project will be completed and put into operation in 2027.

It is known that the biggest difficulty and obstacle of the Chau Doc - Can Tho - Soc Trang Expressway Construction Investment Project Phase 1, Component Project 2, Component Project 3, Component Project 4 is that the sand material source is not guaranteed in terms of volume and exploitation capacity, some sand mines have a large amount of mud so exploitation is ineffective. This is a bottleneck in the project's progress.

In addition, there is a solution to deal with weak soil; currently, the investor is urgently directing consulting units and construction contractors to coordinate surveys to conduct research and adjust design solutions and construction methods to shorten progress.

Source: https://baodautu.vn/thieu-cat-cao-toc-chau-doc---can-tho---soc-trang-qua-dia-ban-can-tho-gap-kho-khan-d414652.html


Comment (0)

No data
No data

Same tag

Same category

Water lilies in flood season
'Fairyland' in Da Nang fascinates people, ranked in the top 20 most beautiful villages in the world
Hanoi's gentle autumn through every small street
Cold wind 'touches the streets', Hanoians invite each other to check-in at the beginning of the season

Same author

Heritage

Figure

Enterprise

Purple of Tam Coc – A magical painting in the heart of Ninh Binh

News

Political System

Destination

Product