Vietnam.vn - Nền tảng quảng bá Việt Nam

“Overcoming the sun, overcoming the rain” at the construction site of the 500 kV Lao Cai - Vinh Yen transmission line project

During the April 30 - May 1 holiday, at the construction site of the Lao Cai - Vinh Yen 500kV transmission line project (section through Lao Cai province), nearly 1,000 workers and technical staff were determined to "overcome the sun and rain", striving to bring the project to the finish line on schedule.

Báo Lào CaiBáo Lào Cai02/05/2025

Construction atmosphere at the construction site of VT24 electric pole, May 1, 2025.

Taking advantage of favorable weather, at the construction site of VT24 electric pole in Xuan Quang commune, Bao Thang district, the construction team of 18 technical staff and workers worked day and night in 3 shifts and 4 shifts. This is a location that is assessed to have difficult terrain and high construction difficulty, so in addition to increased machinery, maximum human resources were also mobilized to complete the entire workload before May 5.

1.jpg
Lao Cai province is constructing 95/100 pole positions.

Mr. Le Van Hong, Head of the Construction Team at VT24, Lao Cai - Vinh Yen 500kV Transmission Line Project shared: " Today is International Labor Day, but under the direction of the investor, the staff and workers of Song Da Construction and Service Joint Stock Company still mobilized 100% of the workforce to construct, trying to ensure safety, progress and quality of the project".

6.jpg
7.jpg
Investors and contractors check construction progress.

Song Da Construction and Service Joint Stock Company was assigned to carry out package No. 1-HH with 51 pole locations. Most of the pole locations are in unfavorable terrain, the unit had to open public roads to bring equipment and machinery into construction. With the initiative of the local government in handing over "clean" land, and the support of people in the project area, the unit is determined to complete the proposed plan early.

Deputy General Director of Song Da Construction and Service Joint Stock Company - Mr. Nguyen Cao Ngoc shared: "We have focused all human resources, machinery and equipment at the construction site and implemented the construction in accordance with the spirit of 3 shifts, 4 shifts, if the working day is not enough, we continue to work at night. Up to this moment, the progress basically meets the plan".

5.jpg
2.jpg
Current progress basically meets the set plan.

Mr. Do Quang Khai, Deputy Director of Power Project Management Board 1 (Vietnam Electricity Group) said that up to now, Lao Cai province is constructing 95/100 locations, the unit is actively working with contractors to remove arising difficulties and speed up the project progress.

Completing the project on schedule assigned by the Prime Minister will not only ensure power transmission and relieve the capacity of hydropower plants in the Northwest region, but also contribute to ensuring national energy security.

The 500kV Lao Cai - Vinh Yen transmission line project has a total investment of nearly 7,420 billion VND, a length of nearly 230 km, passing through 4 provinces: Vinh Phuc, Phu Tho , Lao Cai, Yen Bai. In Lao Cai, the project passes through 2 districts of Bao Thang and Bao Yen with 100 pole locations.

Source: https://baolaocai.vn/vuot-nang-thang-mua-tren-cong-truong-thi-cong-du-an-duong-day-500-kv-lao-cai-vinh-yen-post401137.html


Comment (0)

No data
No data

Same category

Da Nang International Fireworks Festival 2025 (DIFF 2025) is the longest in history
Hundreds of colorful offering trays sold on the occasion of the Duanwu Festival
Ninh Thuan's infinity beach is most beautiful until the end of June, don't miss it!
The yellow color of Tam Coc

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product