Accordingly, in 2025, about 889km of 17 projects invested by the Ministry of Construction will be completed. Among the 12 component projects of the North-South Expressway Phase 2 (2021-2025), the Bai Vot - Ham Nghi, Ham Nghi - Vung Ang, Bung - Van Ninh sections and 70km of the Van Phong - Nha Trang route have been put into operation since April 30.
By August 19, an additional 208km of the expressway will be completed, including the 55km Vung Ang - Bung section; the 65km Van Ninh - Cam Lo section; the 11km Hoa Lien - Tuy Loan section through Da Nang city, running along Ho Chi Minh road; the remaining 13km of the Van Phong - Nha Trang section will also be completed, along with some partially opened sections such as Quang Ngai - Hoai Nhon (10/88km), Hoai Nhon - Quy Nhon (45/70km), Quy Nhon - Chi Thanh (20/62km). The Ministry of Construction aims to complete all remaining North - South expressway component projects by December this year.
Source: https://baodanang.vn/cuc-duong-bo-yeu-cau-ra-soat-tuyen-van-tai-khach-sau-sap-xep-don-vi-hanh-chinh-3265363.html