The project to build the West Thang Long route, the section passing through Dan Phuong district (Hanoi), with a total investment of 1,298 billion VND, is being actively constructed after starting on January 15, 2025. This project is expected to complete the capital's transport system, creating momentum for socio -economic development in the western region.

Project scale and specifications
The project is invested by the Dan Phuong District Construction Investment Project Management Board, with the contractor being the Joint Venture of Deo Ca Construction Joint Stock Company - Deo Ca Group Joint Stock Company. The contract implementation period is 450 days.
- Total length: 5.8 km.
- Total investment: 1,298 billion VND.
- Starting point: Ring Road 3.5.
- End point: Dan Hoai Canal Road.
The cross-sectional scale of the route is divided into two main sections:
- Section 1: From Ring Road 3.5 to Ring Road 4 has a width of 60.5 m.
- Section 2: From Ring Road 4 to Dan Hoai Canal, 40 m wide.

Strategic location and infrastructure connectivity
The investment in the construction of this route aims to concretize the traffic planning approved by the Hanoi People's Council. When completed, the route, together with other sections on the West Thang Long axis, will form a vital, smooth traffic route, connecting from the central urban area (West Lake) to suburban districts such as Dan Phuong, Phuc Tho, Son Tay and Ba Vi.
The project has important intersections with Ring Road 3.5 and Ring Road 4, along with some intersections with local routes such as Road 422 and Tan Hoi Road, creating a complete traffic network, reducing pressure on existing routes.

Impact on the real estate market
Tay Thang Long route passes through an area with many large-scale real estate projects such as Vinhomes Dan Phuong, Noble Tay Thang Long and The Phoenix Garden. The synchronous investment in traffic infrastructure is considered a factor that strongly promotes the value and development potential of these projects as well as the entire real estate market in the West of Hanoi.

Actual construction progress
According to records, the construction work is being actively implemented. Currently, the contractor is focusing on two main sections: the section from Ring Road 3.5 to Road 422 and the section from Tan Hoi Road to Dan Hoai Canal. Many roadbed and drainage items have been gradually completed, clearly forming the future route.



Source: https://baolamdong.vn/dien-mao-truc-tay-thang-long-1300-ty-dong-qua-dan-phuong-398033.html