Power workers handle the power grid at the area where the 110kV pole fell in Phuoc Hiep commune - Photo: PC Da Nang
On the evening of November 1, Da Nang Electricity said that as of 7 p.m. the same day, the entire city had only 10,654 customers whose power supply had not been restored, accounting for about 1.2% of the total 876,552 customers.
To date, more than 260,000 customers have had power restored after the floods; on November 1 alone, the electricity industry restored power to more than 95,000 customers.
Previously flooded areas such as Hoi An, Hoi An Dong, Hoi An Tay, Ban Thach, Huong Tra, Dien Ban, Lien Chieu, Quang Phu wards, and Hoa Phong, Ba Na, Que Phu, Que Son Trung, Tra Tan, Tra Doc, Son Cam Ha communes... have had their electricity completely restored.
Notably, after two days of approaching and handling, the T1 transformer problem at the 110kV Phuoc Son transformer station was resolved, and the station was re-energized in the late afternoon of November 1, helping to stabilize the power supply for the mountainous area in the west of Quang Nam province.

Da Nang Power workers cross the landslide area to approach the landslide that caused pole number 33 of the 110kV line to fall - Photo: PC Da Nang
Phuoc Son 110kV transformer station is the power source serving the mountainous area west of Da Nang city including the communes of Kham Duc, Phuoc Nang, Phuoc Chanh, Phuoc Hiep, Phuoc Thanh.
Previously, as reported by Tuoi Tre Online , due to the impact of heavy rain lasting for many days, a landslide occurred in the mountainous commune of Phuoc Hiep, causing pole No. 33 to fall and breaking the conductors and optical cables of the 110kV line of the Dak Mi 4B - Phuoc Son Hydropower Plant connecting to the 110kV Phuoc Son transformer station.
This incident caused most of the mountainous communes of Phuoc Son district (old) to lose power since October 28.
Due to traffic disruption, it was not until the morning of October 31 that this area could be accessed and the 110kV pole collapse incident could be handled.
Da Nang Electricity said that there are still some areas where power supply has not been restored, mainly in isolated and flooded areas with difficult access such as: Tra Leng, Tra Giap, Nam Tra My, Hung Son, Ha Nha, Nong Son communes...
Source: https://tuoitre.vn/khac-phuc-su-co-nga-cot-110kv-cap-dien-tro-lai-cho-khu-vuc-phia-tay-da-nang-sau-5-ngay-20251101212250237.htm