Provincial leaders inspect the progress of traffic projects.

On the afternoon of June 19, Vice Chairman of the Provincial People's Committee Hoang Phu Hien and the working delegation continued to inspect the works of the Basic Infrastructure Project for Comprehensive Development of Nghe An, Ha Tinh, Quang Binh and Quang Tri Provinces - Nghe An Province Sub-Project in Thai Hoa Town and Vinh City.

Báo Nghệ AnBáo Nghệ An19/06/2025

Clip: Thu Huyen

After inspecting a number of traffic works in Hung Nguyen, Nam Dan, Anh Son, and Con Cuong districts, this afternoon, in Thai Hoa town, the working group inspected the N7 inner-city cross-road sub-project.

The sub-project was approved by the Provincial People's Committee for investment in 2018 and approved for construction drawing design and estimate in 2020 with a total investment of nearly 123.6 billion VND; and was approved by the sponsor, the Asian Development Bank (ADB), to start construction on March 17, 2025.

103dfe21-6b82-4e1b-8b97-50994550d267.jpeg
Vice Chairman of the Provincial People's Committee Hoang Phu Hien and the working delegation inspected the N7 inner-city cross-road sub-project. Photo: Thu Huyen

Route N7 is more than 1 km long, starting point is Km0+00 intersecting with Tran Quoc Hoan Street (old National Highway 48), ending point is Km1+76.95 (intersecting with D1 Street). Up to now, the project has completed compensation payments for 23/26 affected households. Some sections have constructed foundations, drainage ditches... Overall, the project is behind schedule, the construction unit is committed to completing all items on route N7 before September 30, 2025 to ensure traffic connection.

cf383cf5-3e12-4cd4-8e8a-f560b325b353.jpeg
Construction progress of N7 cross-city road in Thai Hoa town is currently slow due to site clearance problems. Photo: Thu Huyen

After inspecting the scene, Vice Chairman of the Provincial People's Committee Hoang Phu Hien requested the People's Committee of Thai Hoa town to strongly mobilize the remaining households to agree to the compensation plan and hand over the site to the investor to ensure the project's progress.

Also this afternoon, the working delegation inspected the sub-project of building and upgrading inner-city roads in Cua Lo, Vinh city. The sub-project was approved by the Provincial People's Committee for investment in 2018 and approved for construction drawing design and estimate in 2020 with a total investment of 124,260 billion VND. Of which, the construction cost is 110,653 billion VND and the site clearance cost is nearly 40 billion VND, approved by ADB to start construction on November 22, 2023.

dd5d7c5a-c4e2-4e8a-bcbb-eaa90642abc0.jpeg
Inspection team of the sub-project to build and upgrade inner-city roads in Cua Lo, Vinh city. Photo: Thu Huyen

In particular, Sao Nam route has a length of 1.1 km, the starting point intersects with National Highway 46), the end point intersects with the National Coastal Road. Currently, the construction of the items on the route has been basically completed, and the sidewalk is under construction. Sao Nam route is expected to be completed on July 15.

Longitudinal route No. 5 has a length of 3.5 km intersecting with Sao Nam Street; the end point intersecting with the 72m Vinh - Cua Lo axis. Branch route N14 is about 300 m long.

68707ad4-c1c0-4d2b-a383-8a6a085fd841.jpeg
Vertical axis route No. 5 from Km0- Km0+70 has not been completed to ensure connection with the intersection with Sao Nam Street due to site clearance problems. Photo: Thu Huyen

At the scene, Vice Chairman of the Provincial People's Committee Hoang Phu Hien requested the Vinh City People's Committee to speed up the progress and complete the site clearance of the vertical axis No. 5 from Km0-Km0+70 to ensure the connection of the road (intersection with Sao Nam Street). At the same time, construct the technical stop at Km2+900, the connection point to the residential road within the implementation period of the Agreement until September 30, 2025.

Currently, the site clearance has been basically completed, and construction has completed 50% of the contract value. There are still 70m of the first line for 03 households. These households have not agreed to the resettlement plan and compensation support plan.

In addition, focus on handing over the site to complete all items on vertical axis No. 5 before September 30, 2025 to ensure traffic connection.

Source: https://baonghean.vn/lanh-dao-tinh-kiem-tra-tien-do-cac-du-an-giao-thong-10299960.html


Comment (0)

No data
No data

Same tag

Same category

Keeping the spirit of Mid-Autumn Festival through the colors of the figurines
Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product