Vietnam.vn - Nền tảng quảng bá Việt Nam

Determined to speed up the progress of key projects in Ho Chi Minh City

On the morning of October 27, Vice Chairman of the Ho Chi Minh City People's Committee Bui Minh Thanh inspected, surveyed the site and listened to reports from localities on the progress of public investment disbursement and site clearance for key projects and works in the city.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng27/10/2025

According to the report, the Ho Chi Minh City Ring Road 4 project from Thu Bien Bridge - Saigon River (passing through the wards: Tay Nam, Long Nguyen, Thoi Hoa, Hoa Loi, Binh Duong, Vinh Tan, Binh Co, Tan Uyen, Bac Tan Uyen and Thuong Tan commune) has a total length of 27.83km, the recovered area is 250.46ha, affecting 1,553 households, individuals and organizations; it is expected to arrange 300 resettlement cases. The capital plan for 2025 is more than 7,307 billion VND. To date, the work of measuring and announcing land recovery has been completed; the drawing appraisal reached 58%, the inventory reached 89%. The People's Committees of localities have approved specific land prices and compensation plans for 268 cases. The area of ​​land handed over reached 13%, the rate of compensation capital disbursement reached 17%.

a thạnh tp ks.jpg
Vice Chairman of Ho Chi Minh City People's Committee Bui Minh Thanh inspected and surveyed land acquisition work to carry out site clearance for Ho Chi Minh City Ring Road 4 Project, the section passing through Binh Co ward.

The Thu Bien - Dat Cuoc road project passing through Thuong Tan commune and Tan Uyen ward (additional 12.5km) has an area of ​​about 27.8 hectares, affecting 165 households, with a planned capital of 549,536 billion VND. Up to now, the land inventory and valuation work has been completed; compensation plans for 44 cases have been approved, 6 cases have been handed over, achieving a disbursement rate of 13%.

The Ho Chi Minh City – Thu Dau Mot – Chon Thanh Expressway Project has a length of 45.7km (passing through the wards: Tan Khanh, Tan Hiep, Vinh Tan, Binh Duong, Binh Co, Phuoc Hoa, An Long, Chanh Phu Hoa and Bau Bang commune), the recovered area is 344.10ha, affecting 1,609 households, the planned capital is 8,000 billion VND. The progress of measurement, counting and drawing appraisal has reached over 95%, the rate of site handover has reached 42%. The disbursement of compensation capital has reached 35% of the plan.

The project to dredge and reinforce Cai stream, Tho Ut bridge section - Dong Nai river (passing through the wards: Binh Duong, Vinh Tan, Tan Hiep, Tan Khanh) is 18.95km long, reclaimed area is 132.8ha, affecting 964 households. Up to now, the land handover rate has reached 87%. The total planned capital is 305 billion VND, disbursed at 80%, expected to be fully disbursed in November 2025.

After listening to the report and conducting a field survey, the leaders of Ho Chi Minh City had a working session with the communes and wards on the progress of site clearance for constructions and projects in the area.

toàn cảnh a thạnh.jpg
Vice Chairman of Ho Chi Minh City People's Committee Bui Minh Thanh works with communes and wards on the progress of site clearance for works and projects in the city.

At the meeting, departments and localities said that there are some difficulties and problems they are facing such as: lack of resettlement land fund; slow progress in editing compensation plan drawings; lack of coordination between the Land Fund Development Center and local authorities, leading to slow handover of land...

local 2.jpg
địa phương.jpg
Representatives of departments and localities spoke at the meeting.
a thạnh tp.jpg
Vice Chairman of Ho Chi Minh City People's Committee Bui Minh Thanh gave a speech at the working session.

Speaking at the meeting, Vice Chairman of the Ho Chi Minh City People's Committee Bui Minh Thanh praised the localities for their great efforts in disbursing public investment and site clearance for key projects. At the same time, he requested the City Land Fund Development Center to coordinate with relevant departments and localities to promptly complete legal procedures, especially the approval of compensation plans, conversion of forest use purposes and site acceptance to ensure the progress of the construction of the Ho Chi Minh City Ring Road 4 project before October 31, 2025.

In addition, the Vice Chairman of the Ho Chi Minh City People's Committee requested departments and localities to be more determined to speed up the progress of projects. In particular, resettlement work must be given special attention, ensuring that the lives of people in the new place must be equal to or better than the old place...

Source: https://www.sggp.org.vn/quyet-tam-day-nhanh-tien-do-cac-cong-trinh-du-an-trong-diem-tren-dia-ban-tphcm-post820223.html


Comment (0)

No data
No data

Same tag

Same category

Dong Van Stone Plateau - a rare 'living geological museum' in the world
Watch Vietnam's coastal city make it into the world's top destinations in 2026
Admire 'Ha Long Bay on land' just entered the top favorite destinations in the world
Lotus flowers 'dyeing' Ninh Binh pink from above

Same author

Heritage

Figure

Enterprise

High-rise buildings in Ho Chi Minh City are shrouded in fog.

News

Political System

Destination

Product