Rach Mieu 2 Bridge progress reaches over 86% of plan

On May 18, Mr. Tran Van Thi, Director of My Thuan Project Management Board, said that up to now, the overall progress of the Rach Mieu 2 Bridge Construction Investment Project (connecting Tien Giang and Ben Tre provinces) has reached more than 86%, exceeding the general progress by more than 2% compared to the plan; the main bridge - Rach Mieu 2 Bridge is exceeding the progress by more than 8%.

Báo Sài Gòn Giải phóngBáo Sài Gòn Giải phóng18/05/2025

z6517589127343_1ed9d1c747920312161bcc5c0a0e5feb.jpg
The main bridge section - Rach Mieu 2 bridge is 8% ahead of schedule.

Accordingly, the construction section is 100% complete on the entire 14km route length. The construction unit is currently unloading, spreading asphalt concrete... and will complete the entire route on the Ben Tre side, the road leading to Rach Mieu 2 bridge before June 30.

The bridge section on the route has completed 4/6 bridges (Xoai Hot bridge, My Tho bridge, Tam Son bridge and Ba Lai bridge), the remaining 2 bridges are under construction (Rach Mieu 2 main bridge and Song Ma bridge), of which Song Ma bridge will be completed before June.

The main bridge - Rach Mieu 2 bridge is under construction with finishing items such as: railing edge, median strip, lighting, bridge deck expansion joints...

A2- THI CONG RM2 BTRE.jpg
The construction of the approach road of Rach Mieu 2 Bridge Project is 100% complete on the entire length of the route 14/14km. Currently, the construction unit is unloading and spreading asphalt concrete.

Currently, at the construction site, the units continue to maintain the implementation of 3 shifts, 4 teams (with 30 construction teams; about 150 construction equipment; 500 workers and 83 technical staff). All are determined to complete the project as directed by the Prime Minister .

Mr. Tran Van Thi informed that, following the instructions of the Prime Minister, with the spirit of "promised is done, committed is done". Recently, My Thuan Project Management Board together with all construction units and supervision consultants have strictly implemented the instructions of the Prime Minister to organize construction "3 shifts 4 shifts", "overcome the sun and overcome the rain", at the same time, organize and launch the emulation movement "75 days and nights to speed up the progress of completing the Rach Mieu 2 Bridge Project" to speed up the progress further, towards completing the project according to the Prime Minister's opinion.

z6494720793692_190d64398f96bf7504a792370df584c1.jpg
Overall progress of the Rach Mieu 2 Bridge Construction Investment Project (connecting Tien Giang and Ben Tre provinces) reached more than 86%, exceeding the overall progress by more than 2% compared to the plan.

Rach Mieu 2 Bridge project has a total length of more than 17.6km, starting at Dong Tam intersection (intersection between National Highway 1 and Provincial Road 870) in Chau Thanh district, Tien Giang province; ending at Km16+660 National Highway 60, in Ben Tre city, Ben Tre province, about 0.71km from Ham Luong bridge, started construction in March 2022.

Source: https://www.sggp.org.vn/tien-do-cau-rach-mieu-2-dat-tren-86-ke-hoach-post795784.html


Comment (0)

No data
No data

Same category

The fiery red sunrise scene at Ngu Chi Son
10,000 antiques take you back to old Saigon
The place where Uncle Ho read the Declaration of Independence
Where President Ho Chi Minh read the Declaration of Independence

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product