Dong Dang - Tra Linh Expressway: Efforts to overcome difficulties, speeding up day and night to keep up with progress

As the flood has just receded, the investor and contractor of the Dong Dang - Tra Linh expressway project (through Lang Son and Cao Bang provinces) have organized construction day and night, determined to open phase 1 by the end of 2025.

Báo Tin TứcBáo Tin Tức02/11/2025

Recently, continuous heavy rains in Lang Son and Cao Bang have greatly affected the construction progress of the Dong Dang - Tra Linh expressway project. For example, at the end of September, a flash flood suddenly appeared in the area of ​​the Project Management Board in Duc Long commune (Cao Bang), killing 3 officers and engineers, as well as completely destroying the residential area and kitchen...

Overcoming difficulties in weather and terrain, investors and contractors have mobilized and deployed over 276 construction sites with a total of 1,487 machines and equipment and about 3,332 engineers and workers simultaneously approaching and organizing construction day and night on the handed-over land segments, striving to complete the goal of partially opening the first phase of the project in December 2025 as directed by the Prime Minister .

Photo caption
The Dong Dang - Tra Linh Expressway project has a total length of 121 km, with a total investment of nearly VND 23,000 billion, in the form of public-private partnership (PPP).
Photo caption
Phase 1 of the 93.35 km long project includes two tunnels through the mountain...
Photo caption
...and 64 overpasses spanning the Ky Cung and Bang Giang rivers, along with countless streams and provincial roads.
Photo caption
With karst geological structure and rugged terrain, the Ministry of Construction assesses the Dong Dang - Tra Linh expressway project as one of the most challenging traffic projects in the country today.
Photo caption
Dong Dang - Tra Linh Expressway section through Lang Son province is being accelerated.
Photo caption
The contractor is rolling some sections of the Dong Dang - Tra Linh expressway at IC01 intersection (Km0+400) in Hoang Van Thu commune, Lang Son province, expected to open to traffic at the end of 2025.

Discussing the difficulties of the project, Mr. Nguyen Duc Tuan, Deputy General Director of Dong Dang - Tra Linh Expressway Joint Stock Company, said that currently, the site clearance work has been handed over by Lang Son and Cao Bang provinces to about 99%, however, some segments are still in a state of "poor rice and beans".

Enterprises recommend that localities promptly complete site clearance work, relocate technical infrastructure, hand over all clean sites, dumping sites, etc.; at the same time, stabilize the supply and price of materials for investors and contractors to organize construction, ensuring completion on schedule.

Regarding this issue, on October 28, 2025, the Ministry of Construction sent a document to the People's Committees of Lang Son and Cao Bang provinces to thoroughly resolve problems and speed up the progress of the Dong Dang - Tra Linh expressway. In addition to the local site clearance work, the Ministry of Construction also requires construction units not to ignore the quality of the project for reasons of progress. Important items such as large bridges, tunnels and locations with potential risks of landslides must be closely inspected and monitored...

Photo caption
Phase 2 of the project will expand the 93.35 km invested in phase 1 and build a new 27.71 km of highway connecting to Tra Linh border gate.
Photo caption
Investors and contractors mobilized maximum human resources and machinery to organize construction day and night to speed up the progress of the entire project.
Photo caption
More than 3,300 engineers and workers braved the sun and rain to construct the Dong Dang - Tra Linh expressway project.
Photo caption
Phase 1 of the Dong Dang - Tra Linh expressway project is expected to be completed by the end of 2026, and phase 2 will be completed in December 2027.
Photo caption
When the project is completed, travel time by car between Hanoi and Cao Bang will be only 3.5 hours instead of 6 - 7 hours as at present.

According to Mr. Nguyen Thy Hung, Deputy Director of the Bidding Management Department (Ministry of Finance), the Dong Dang - Tra Linh Expressway project is a true model of public-private partnership (PPP), demonstrating the joint responsibility between the State, enterprises and localities in project implementation. In particular, with the PPP++ model, project investment capital is mobilized from many different sources, increasing mobilization efficiency and minimizing risks throughout the project implementation process.

Chairman of Cao Bang Provincial People's Committee Le Hai Hoa assessed that the Dong Dang - Tra Linh expressway project, once completed, will not only open up a new future for the revolutionary homeland, but also contribute to the implementation of the country's strategic goal of completing 3,000 km of expressway from Cao Bang to Ca Mau cape - a continuous connecting axis, raising the country's position.

Source: https://baotintuc.vn/xa-hoi/cao-toc-dong-dang-tra-linh-no-luc-vuot-kho-tang-toc-ngay-dem-de-kip-tien-do-20251031084012684.htm


Comment (0)

No data
No data

Same tag

Same category

Captivating beauty of Sa Pa in 'cloud hunting' season
Each river - a journey
Ho Chi Minh City attracts investment from FDI enterprises in new opportunities
Historic floods in Hoi An, seen from a military plane of the Ministry of National Defense

Same author

Heritage

Figure

Enterprise

One Pillar Pagoda of Hoa Lu

News

Political System

Destination

Product