Working scene.
Actively implement tasks
Speaking at the working session, Chairman of An Giang Provincial People's Committee Ho Van Mung requested provincial and local departments, branches and sectors to uphold their sense of responsibility and focus on urgently reviewing each project and work, resolutely removing difficulties and obstacles in procedures, capital, materials, site clearance, etc., to ensure the progress and quality of projects and works according to the Central Government's direction.
The Chairman of the Provincial People's Committee emphasized the spirit of initiative and personal responsibility associated with assigned tasks, and at the same time requested units to strengthen coordination and report promptly on the progress of serving the APEC Summit 2027. With political determination and consensus, An Giang will complete the progress of works and projects to serve the APEC Summit 2027.
Alternate member of the Party Central Committee, Deputy Secretary of the Provincial Party Committee, Chairman of the People's Committee of An Giang province Ho Van Mung spoke at the working session.
Chairman of the People's Committee of An Giang province Ho Van Mung emphasized that Phu Quoc special economic zone needs to make efforts, actively focus on implementing, and continue to make efforts to complete assigned tasks related to projects and works serving the APEC 2027 Conference. At the same time, Phu Quoc special economic zone is required to report the progress of site clearance for assigned projects on a weekly basis, promptly reflect difficulties and problems so that the province can direct departments and branches to remove them, ensuring the overall progress of the projects...
5 projects achieved and exceeded schedule
According to the Provincial People's Committee, An Giang always seriously and urgently implements the directions of the Central Government, the Government, and Deputy Prime Minister Nguyen Chi Dung, focusing on preparing well for investment work, implementing projects, upgrading facilities and infrastructure to prepare good conditions to serve the APEC 2027 Conference.
Provincial Party Committee member, Director of An Giang Provincial Department of Finance Pham Minh Tam spoke at the meeting.
Director of An Giang Province Department of Construction Le Viet Bac spoke.
Of the 21 projects under Decision No. 948/QD-TTg of the Prime Minister, to date, investors have been selected for 6 non-budget projects and 7 public investment projects have been approved (of which construction contractors have been selected for 3 projects).
Of these, 5 projects achieved and exceeded the set schedule, including: Investment in expanding Phu Quoc Airport, Bai Dat Do Urban Area, Nui Ong Quan Urban Area, construction of underground technical infrastructure in An Thoi area; construction of underground technical infrastructure in Duong Dong area.
Public investment projects serving APEC are allocated capital to be implemented in 2025 with a total of 4,216,194 million VND. Of which, the central budget capital is 2,751,000 million VND, the local budget capital is 1,465,195 million VND. By August 31, 2025, 537,331 million VND had been disbursed.
Sun Group representative speaking at the meeting.
Regarding the supply of construction materials, the province has adjusted the mineral planning, adding 2 mines of materials for filling from the sea to serve the APEC Conference 2027. To serve the APEC Conference 2027, the total expected demand for the projects: Sand for filling is about 16,346,231m 3 , various types of stone are about 4,826,152m 3 , and earth for filling is about 5,214,371m 3 . |
The People's Committee of An Giang province has directed sectors and localities to develop plans for land acquisition, compensation, support, resettlement and site clearance; forest inventory and conversion; and preparation of materials and minerals to implement investment projects and works.
Construction of Phu Quoc International Airport expansion investment project.
Workers constructing the APEC 2027 Conference Center project.
The Provincial People's Committee has assigned specific tasks to each unit under the department, assigned specific responsibilities to each individual, and implementation time for each stage associated with each specific project and construction serving APEC. In particular, 15 surveying teams have been established, and plans for compensation, support, resettlement and site clearance have been made. At the same time, cadastral records of each project have been extracted to prepare for issuing a revocation notice.
News and photos: TAY HO