Deputy Secretary of the City Party Committee, Chairman of the City People's Committee Pham Duc An chaired the meeting. Also attending were Permanent Vice Chairman of the City People's Committee Ho Ky Minh and Vice Chairman of the City People's Committee Tran Nam Hung.
According to the report of the Department of Finance, the total public investment capital plan for 2025 assigned by the Prime Minister to the city is more than 16,400 billion VND. Meanwhile, the People's Council and People's Committee of the city assigned more than 17,600 billion VND.
Since the beginning of the year, the city has allocated 17,074 billion VND in detail to units and localities, reaching 96.8% of the capital plan assigned by the People's Council.
According to data from the State Treasury of Region XIII, as of November 7, the city has disbursed VND8,697 billion out of the total VND16,402 billion of the 2025 capital plan assigned by the Prime Minister, reaching 53%. For the capital plan assigned by the City People's Council (VND17,638 billion), the disbursed amount is VND8,632 billion, reaching 49.3%.

To ensure the disbursement rate of 100% of the capital plan assigned by the Prime Minister, the city still has to disburse 7,705 billion VND by January 31, 2026.
It is estimated that by November 30, 2025, the disbursement of the 2025 capital budget plan will reach VND 10,660 billion out of the total VND 16,402 billion assigned by the Prime Minister, equivalent to 65%.
In addition, VND689 billion from the 2024 capital plan was disbursed in 2025, reaching 44.9% of the total VND1,534 billion extended.
For the Project Management Boards under the City People's Committee (excluding 24 regional management boards), the total capital plan for 2025 is VND 8,447 billion. As of October 31, these boards have disbursed VND 4,535 billion, reaching 53.7%. The remaining capital to be disbursed by January 31, 2026 is VND 3,911 billion.
For 24 regional management boards, the total capital plan for 2025 is VND5,399 billion. As of October 31, the disbursed capital was VND2,201 billion, reaching 40.76%. The remaining VND3,198 billion needs to be disbursed before January 31, 2026.

Regarding disbursement of departments, branches and sectors under the City People's Committee, the total capital plan for 2025 for these 35 agencies and units (including departments, branches and some other agencies) is 2,160 billion VND.
As of October 31, VND1,146 billion had been disbursed, reaching 53.07%. The remaining capital to be disbursed by January 31, 2026 is VND1,013 billion.
For wards, communes, and special zones under the City People's Committee, the total capital plan allocated in 2025 to these 94 units is VND1,282 billion. As of October 31, more than VND743 billion had been disbursed, reaching 65.7%. The remaining capital to be disbursed by January 31, 2026 is VND387 billion.
Regarding the implementation of key projects, creating momentum for socio -economic development of Da Nang city in the period of 2021 - 2025, the estimated capital plan for 2025 allocated for these projects is 3,946 billion VND.
As of October 31, 1,804 billion VND had been disbursed, reaching 46% of the assigned plan. In the period of 2021 - 2025, the city has 29 key projects, including 24 projects in Da Nang (old) and 5 projects in Quang Nam (old).
Since the beginning of the year, the Department of Finance has compiled and advised the City People's Committee on 16 internal adjustments to the 2025 public investment capital plan and the medium-term public investment capital plan for the 2021-2025 period. Currently, 30 units have sent documents requesting continued internal adjustments to the 2025 public investment capital plan, with a total adjustment requirement of 1,126 billion VND.
Regarding the medium-term public investment plan for the period 2026 - 2030 of Da Nang city, the total expected source is 118,000 billion VND. Of which, the central budget accounts for 34,800 billion VND and the local budget is 83,200 billion VND.
Concluding the meeting, Chairman of the City People's Committee Pham Duc An requested agencies, units and localities to clearly understand each specific problem in the disbursement of public investment capital. He emphasized the need for close coordination, avoiding fear of collision, contact or cooperation. Each agency, unit and locality must be responsible for organizing implementation. In case of failure to complete the task, it will be assessed as unsatisfactory. For projects lacking materials, new regulations must be promptly applied to handle. Any problems arising must be proposed and resolved immediately, without waiting.
Regarding site clearance, relevant agencies need to proactively review the progress of issuing unified regulations after the province merger to speed up implementation.
Communes and wards need to review all data on medium-term public investment plans, compile and report to the city to complete the content before the year-end meeting of the City People's Council.
Agencies and units must be determined and resolute in carrying out the disbursement task in 2025, aiming to achieve the highest disbursement rate of public investment capital for the city.
The Chairman of the City People's Committee requested that each agency, unit, and locality must clearly present specific problems and propose solutions. Cases beyond authority must be promptly proposed and reported to superiors for consideration and resolution. Absolutely do not let rigidity and machinery cause delays and create more problems.
Source: https://baodanang.vn/den-thang-11-2025-da-nang-giai-ngan-von-dau-tu-cong-dat-53-3309482.html