The Vice Chairman of the Provincial People's Committee chaired the working session with units and localities. |
According to the Report of the People's Committee of Bach Quang Ward, the Song Cong II Industrial Park Project, Phase 1, started in 2018 and temporarily stopped construction. By early 2025, the Project continued to be implemented, by September 4, 2025, 238.56/249.52 hectares (reaching 95.6%), and 10.96 hectares (of 50 households and 1 organization) had not been cleared. The reason was due to problems with the unit price of compensation for agricultural land, residential land and the value of perennial trees; some households had not yet accepted the compensation plan.
Song Cong II Industrial Park Project Phase 2 has an area of 296.24 hectares, divided into 2 areas. Of which, area 1 has an area of 175.52 hectares, and has basically completed the inventory and list of resettled households; area 2 has an area of 120.72 hectares, with 120.45/120.72 hectares (99.78%) of land clearance completed, the remaining 1.19 hectares are waiting for the second phase of land allocation.
Currently, there are still 12/132 graves that have not been relocated. For resettlement projects including: Technical infrastructure project for resettlement area serving site clearance of Song Cong II Industrial Park (21.74ha), 16.44ha has been cleared (75.6%). Some other resettlement areas (Tan Quang, Tan Tien, residential area No. 1 Bach Quang...) are in the implementation phase, but progress is slow, technical infrastructure is not yet complete.
Comrade Bui Van Luong inspected the site of the resettlement area. |
Concluding the inspection, the Vice Chairman of the Provincial People's Committee affirmed: The viewpoint and policy on implementing the Industrial Park have been clear, so there needs to be specific actions so that the project can soon be put into operation, attract businesses, and promote local socio -economic development.
The Vice Chairman of the Provincial People's Committee requested the Industrial Park Management Board to speed up the progress of infrastructure completion, coordinate with the Land Fund Development Center and Bach Quang Ward to mobilize households to receive compensation money, hand over clean land; the area with land needs to be urgently constructed and disbursed investment capital.
Regarding resettlement areas, the Vice Chairman of the Provincial People's Committee requested the Industrial Park Management Board to promptly complete project adjustments and submit compensation plans for approval. The Land Fund Development Center is responsible for completing documents, procedures, designs, and bidding according to regulations; coordinating with the People's Committee of Bach Quang Ward to review compensation decisions and ensure people's rights.
For Viglacera Joint Stock Company - the investor of Song Cong II Industrial Park Phase 2, the Vice Chairman of the Provincial People's Committee requested to urgently implement the approved items and fully fulfill financial obligations. Coordinate with the locality and departments and branches to resolve problems related to resettlement, site clearance, prepare resources to pay compensation, and actively promote investment, creating a favorable environment to ensure the progress and effectiveness of the project.
Before working with relevant units, the Vice Chairman of the Provincial People's Committee inspected the resettlement area of Song Cong II Industrial Park; infrastructure of Song Cong II Industrial Park and Ba Xuyen - Tan Quang cemetery... to grasp the project implementation situation and difficulties in the implementation process.
Source: https://baothainguyen.vn/thoi-su-thai-nguyen/202509/hanh-dong-quyet-liet-som-hoan-thanh-du-an-khu-cong-nghiep-song-cong-ii-fe34a68/