The Tan Duc Industrial Park Infrastructure Investment, Construction and Business Project has an area of 300 hectares (located in Tan Minh commune, Lam Dong province) invested by Sonadezi Binh Thuan Joint Stock Company. Currently, the project's phase 1 items have been basically completed at about 90% of the volume such as: internal traffic routes, wastewater treatment plant, booster pumping station, water supply pumping station, lighting system, planting trees along the road...
According to the Provincial Industrial Park Management Board, up to now, the Tan Duc Industrial Park project has been decided by the Provincial People's Committee to lease land to the investor in 3 phases with a total area of 288.51 ha/300 ha, reaching more than 96% of the total industrial park land area. Regarding investment attraction, Sonadezi Binh Thuan Joint Stock Company said that recently, it has signed land lease agreements (about 58.22 ha) with 11 domestic and foreign invested enterprises. At present, this industrial park has initially attracted 3 investment projects (including 2 domestic projects, 1 FDI project) with a total registered capital of 725 billion VND and 3.5 million USD... In the near future, the investor will continue to work with customers to survey and explore opportunities to implement secondary projects, moving towards signing land lease agreements to contribute to increasing the occupancy rate of the industrial park.
In addition to accelerating the progress of infrastructure completion to attract secondary projects, the issue of ensuring power supply for production and business activities in Tan Duc Industrial Park is also taken into account. That is the Tan Duc 110 kV transformer station and the Ham Tan 2 - Tan Duc 110 kV transmission line with an estimated total investment of about 287 billion VND has been started. This project is invested by the Southern Power Corporation, with a capacity of 2x40 MVA (the first phase will install a capacity of 1x40 MVA) with a connecting line consisting of 2 conductors 26.3 km long.
According to the implementation progress of the Southern Power Project Management Board (under the Southern Power Corporation), after completing the preparation work, the project is expected to start construction in March 2026 and be energized in September 2026... However, during the implementation process, the Tan Duc 110 kV Transformer Station project and the Ham Tan 2 - Tan Duc 110 kV line are currently facing some difficulties that need to be coordinated to resolve. Specifically, the proposed land location for the project has an area that is not suitable for land use planning and overlaps the Tan Duc Industrial Park project, or a part of the 110 kV line section in Phuoc Hoi ward is currently not suitable for construction planning...
Therefore, recently, the Southern Power Corporation has proposed the Provincial People's Committee to support and direct relevant departments and branches to promptly update the project into the local land use planning. Due to the urgency of power supply in the period of 2025 and after 2025, the electricity sector also proposed the Provincial People's Committee to consider and unanimously approve the decision to approve the investment policy. At the same time, approve the investor for the project in parallel with updating the local planning this year, thereby creating conditions for the project to be implemented soon... On the electricity sector side, the Southern Power Corporation commits to continue to coordinate in providing data to departments, branches, and local areas to update the project into relevant planning under the direction of the Provincial People's Committee.
Recently, at the meeting to hear the report on the project's progress, Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee Nguyen Hong Hai said that this is a very important project to provide electricity for production and business activities in Tan Duc Industrial Park. In order to promptly implement, the Provincial People's Committee leader requested the investor to have a written explanation, clarifying some contents on planning, route direction... Thereby, sending it to the competent department for timely re-evaluation, collecting opinions from relevant parties and soon having a report to submit to the Provincial People's Committee for consideration and approval according to regulations.