Specifically, the emergency deployment will be carried out within 90 days, with a budget of 2.9 billion VND from Lam Dong province's budget reserve.
Duc Trong Regional Construction Investment Project Management Board manages and implements the project.

Lam Dong Provincial People's Committee requests the Duc Trong Area Construction Investment Project Management Board to shorten the emergency construction time based on the urgency and the level of impact of the project on the safety of the downstream area, in order to promptly Timely implementation of necessary measures to ensure absolute safety for the project in the shortest time.

According to Lam Dong Provincial People's Committee, the urgent construction is to ensure safety during the operation of Cay An Lake irrigation project, avoiding the risk of dam insecurity and dam failure.
At the same time, it protects the lives of about 400 households and 200 hectares of agricultural land in the downstream area of the reservoir.

As reported by SGGP, Cay An Lake in Ta Nang Commune was put into use in 2007 with a capacity of about 1.7 million m3 . For many weeks now, the downstream area of the left shoulder of the main dam has seen localized sliding, forming cracks, with groundwater seeping through the foot of the dam.
In addition, at some other locations of the main dam, there is also water seepage and water leakage.
Source: https://www.sggp.org.vn/lam-dong-khan-cap-xay-dung-cong-trinh-chong-tham-sat-truot-ho-cay-an-post822385.html






Comment (0)