The project has a total investment of 160 billion VND, approved for investment policy adjustment in August 2021, with implementation period from 2022 - 2025. The project investor is Construction Investment Project Management Board (PMB) No. 3.
During the process of completing procedures, specialized agencies discovered many problems related to mineral planning and urban planning.
Accordingly, in the total area of nearly 38 hectares of land planned for construction, about 21 hectares are located within the closed boundary of Dak Nia bauxite mine and more than 10 hectares are in the planning area for green trees - ecological park.
For the project to be eligible for implementation, it is necessary to handle overlapping bauxite mine planning and adjust more than 10 hectares of green land to commercial and service purposes.
Although the investor has taken steps to resolve difficulties after the policy was issued, the progress is still very slow. The project has been allocated more than 1.1 billion VND and has disbursed more than 0.5 billion VND.
Lam Dong Department of Construction stated that the suspension of the project was necessary in the context of administrative unit arrangement, to avoid wasting public investment. At the same time, the Department proposed the Provincial People's Committee to consider approving the suspension and settle the costs that have been implemented.
Project Management Board No. 3 is currently the investor of 36 projects in the western region of Lam Dong (in the old Dak Nong area) with a total investment of nearly 18,000 billion VND. In addition to the proposed suspension of the multi-purpose stadium, other projects are still being implemented according to schedule.
Source: https://baolamdong.vn/lam-dong-kien-nghi-tam-dung-du-an-nha-thi-dau-da-nang-160-ty-dong-399810.html