Up to now, the progress of the projects has basically met the requirements, but there are still many difficulties that need to be resolved to speed up the progress.
More than 90% of households have been counted.
Mr. Huynh Van Minh, Deputy Director of Lam Dong Provincial Land Fund Development Center, said: Implementing the direction of Lam Dong Provincial People's Committee and the Steering Committee for implementing key projects and works of the province, the unit is coordinating with localities to actively carry out site clearance for the two expressway projects Bao Loc - Lien Khuong and Tan Phu - Bao Loc.

Specifically, in Ward 1 Bao Loc, the project has a route length of 4.82km, a reclaimed area of 36.82ha, affecting 150 households and 1 organization. To date, the inventory work has been completed 100% (151 households); of which, 50/100 files have been reviewed, 40 households are eligible for compensation.
Bao Lam 2 Commune has a route length of 6.46km, a reclaimed area of 53.57ha, involving 176 households and 2 organizations. The locality has counted 165 households (reaching 92.7%) and held meetings to review 110/150 records.
In Hoa Ninh commune, the total length of the route is 3.66km, the recovered area is 30.7ha, affecting 116 households. The Di Linh Area Construction Investment Project Management Board has completed 100% of the inventory, reviewed 87/102 records, and 60 households are eligible for compensation.

Di Linh commune has a route length of 12.53km, the recovered area is 138.46ha, affecting 509 households. Currently, 468 households (91.8%), 154 files have been transferred to the commune People's Committee and 110 households have been considered.
In Bao Thuan commune, the route is 8.37km long, the recovered area is 71.73ha, affecting 303 households and 2 organizations. Up to now, 282 households (92.5%), 56 files have been transferred to the Commune People's Committee to meet to consider the origin of the land.
Gia Hiep commune has 6.62km of route passing through the area, with an area of 68.14 hectares, affecting 228 households. Currently, 200 households (87.7%) have been counted and the dossier is being completed to send to the commune People's Committee for consideration.
In Ninh Gia commune, the route is 9.82km long, the recovered area is 57.4ha, affecting 131 households and 3 organizations. Up to now, 112 households (91.1%), 85 files have been transferred to the commune People's Committee, and 22 households have been considered. However, there are still 12 households and 1 organization that have not been counted because they could not be contacted.

In Duc Trong commune, the route length is 10.33km with a total recovered land area of 71.15ha including 400 households and individuals. Currently, 368 households and individuals have been counted (92.0%); 182 files have been transferred to the Commune People's Committee for a meeting to review the origin; 85/182 households have been reviewed; of which, 50 households are eligible.
Tan Hoi Commune has 142 households affected along a total route length of 3.15km. Up to now, the count has been almost completed (99.3%), but there are still 7 cases that have not been contacted due to transfer procedures.
In Hiep Thanh commune, the route is 7.6km long, the recovered area is 48.1ha, affecting 302 households. The inventory work reached 94.4%, 100 files have been transferred to the commune People's Committee for consideration, 50 files have been reviewed. However, the locality still has more than 40 plots of land whose users have not been identified due to multiple transfers and the landowners' absence from the locality.
Currently, the land price development plan has been submitted to the People's Committees of communes and wards such as Ward 1 Bao Loc, Bao Lam 2, Ninh Gia, Tan Hoi. It is expected that in Duc Trong, it will be submitted in early November 2025. The remaining localities are hiring consulting units to complete it.
Ensure project progress
In parallel with the Bao Loc - Lien Khuong project, the inventory work for the Tan Phu - Bao Loc expressway project is also being actively implemented.
Specifically, in Ward 1 Bao Loc, the route length is 4.86 m, affecting 202 households, currently only 36.9% has been counted; Ward 2 Bao Loc is 16.52 km long, affecting 411 households, and 36.1% has been counted.

In Da Huoai commune, the count reached 20.5%; Da Huoai 2 commune has issued a notice of land recovery for two organizations; Da Teh 2 commune has a route length of 18km, affecting 149 households, and is currently completing the dossier.

According to Mr. Huynh Van Minh, Deputy Director of Lam Dong Province Land Fund Development Center, although the progress of site clearance has achieved many results, there are still many difficulties and problems.
Specifically, the actual boundaries of many plots of land are different from the cadastral map, so they need to be re-measured and adjusted. Many households live outside the province, so it is difficult to contact and count. The mountainous terrain is complex, making it difficult to move around. The custom of dividing land within the family and not yet completing the name transfer procedure also makes it time-consuming to confirm the origin of the land.

The Provincial Land Fund Development Center recommends that the Department of Agriculture and Environment direct the Provincial Land Registration Office to coordinate and support the adjustment and updating of cadastral maps to suit actual use, creating conditions for localities to complete the inventory work, prepare compensation records and submit for approval on schedule.
Accelerating compensation and site clearance is crucial to the progress of the construction of the two key expressway projects Bao Loc - Lien Khuong and Tan Phu - Bao Loc. These are strategic traffic routes of Lam Dong province, contributing to regional connectivity, promoting socio- economic development and creating a driving force for sustainable growth in the Southern Central Highlands region.
Source: https://baolamdong.vn/lam-dong-tang-toc-giai-phong-mat-bang-hai-du-an-cao-toc-399540.html






Comment (0)