Promoting the disbursement progress of public investment capital in 2025 in Da Lat and Lac Duong areas

On the afternoon of September 15, Mr. Vo Ngoc Hiep, Vice Chairman of the Provincial People's Committee, chaired a meeting to seek solutions to promote the disbursement progress of public investment capital in 2025 in Da Lat and Lac Duong.

Báo Lâm ĐồngBáo Lâm Đồng15/09/2025

afternoon-view.jpg
The meeting was attended by representatives of relevant departments, branches and sectors, and local leaders.

Attending the meeting were leaders of relevant departments, the Management Board of Investment and Construction Projects in Da Lat and Lac Duong areas; leaders of wards in Da Lat and Lac Duong areas.

Leaders of the Da Lat Area Construction Investment Project Management Board reported on the progress of disbursement of public investment capital for assigned projects.
Leaders of the Da Lat Area Construction Investment Project Management Board reported on the progress of disbursement of public investment capital for assigned projects.

According to the report from the Da Lat Area Construction Investment Project Management Board, the total public investment capital allocated in the year was nearly 416 billion VND, implemented on 52 projects. As of the end of June, the disbursement rate reached 48.11% (equivalent to nearly 200 billion VND). According to the Board's report, many projects are stuck in compensation and site clearance, especially the fact that the resettlement land price has not been determined.

Leaders of the Lac Duong Area Construction Investment Project Management Board reported on the progress of disbursement of public investment capital for assigned projects.
Leaders of the Lac Duong Area Construction Investment Project Management Board reported on the progress of disbursement of public investment capital for assigned projects.

In Lac Duong, the Lac Duong Area Construction Investment Project Management Board is implementing 22 projects with a total investment of more than VND89 billion. As of the end of July, the disbursement rate reached 17.4%, equivalent to VND15.47 billion. The project to upgrade and expand 19/5 Street in particular is facing difficulties due to the lack of consensus with some households on the compensation plan.

Leaders of Xuan Truong Ward People's Committee - Da Lat reported on the progress of the resettlement area on Huynh Tan Phat Street, belt road project.
Leaders of Xuan Truong Ward People's Committee - Da Lat reported on the progress of the resettlement area on Huynh Tan Phat Street, the belt road project.

The meeting also recorded reports from ward representatives on land clearance mobilization work and related recommendations and proposals. Leaders of the People's Committees of Xuan Truong-Da Lat, Lam Vien-Da Lat, Xuan Huong-Da Lat wards also reported in detail on the progress of project implementation in the area.

Representatives of the Department of Finance responded to a number of recommendations from the Committees and wards and expressed their opinions and recommendations at the working session.
Representatives of the Department of Finance responded to a number of recommendations from the Committees and wards.

Concluding the meeting, comrade Vo Ngoc Hiep emphasized: The disbursement rate of public investment capital for projects in Da Lat and Lac Duong areas is high compared to the provincial average. However, there are still problems that need to be resolved in each project. He also "named" a number of investment projects from the provincial budget that are still being delayed, such as the project from Lu Gia Street to the upper stream of Xuan Huong Lake, Hoang Van Thu Street, Yersin Park...

Comrade Vo Ngoc Hiep, Vice Chairman of the Provincial People's Committee chaired the meeting.
Comrade Vo Ngoc Hiep, Vice Chairman of the Provincial People's Committee chaired the meeting.

The Vice Chairman of the Provincial People's Committee also pointed out a number of problems and shortcomings and directed relevant units to focus on reviewing and evaluating each project, clearly identifying the locations of the problems to have timely solutions to remove them and promote project progress.

"From now until the end of the year, we must make efforts to disburse public investment capital for 2025 and capital transferred from 2024," Comrade Vo Ngoc Hiep emphasized.

For completed projects, urgently complete disbursement. For projects preparing for investment, promptly complete documents and submit to competent authorities for early approval of investment policies.

Ward leaders attended the meeting
Ward leaders attended the meeting

For unfinished construction projects, it is required to strictly implement the direction of the Provincial People's Committee leaders, closely review and speed up the progress of each project and each construction.

He also directed project investors to proactively coordinate with the People's Committees of wards and communes to do a good job of site clearance and resettlement arrangements for people affected by the projects.

Wards and communes must complete land prices for compensation and site clearance work within September.

Source: https://baolamdong.vn/thuc-day-tien-do-giai-ngan-von-dau-tu-cong-nam-2025-tren-dia-ban-da-lat-va-lac-duong-391520.html


Comment (0)

No data
No data

Same tag

Same category

Captivating beauty of Sa Pa in 'cloud hunting' season
Each river - a journey
Ho Chi Minh City attracts investment from FDI enterprises in new opportunities
Historic floods in Hoi An, seen from a military plane of the Ministry of National Defense

Same author

Heritage

Figure

Enterprise

One Pillar Pagoda of Hoa Lu

News

Political System

Destination

Product