Attending the meeting were leaders of relevant departments, the Management Board of Investment and Construction Projects in Da Lat and Lac Duong areas; leaders of wards in Da Lat and Lac Duong areas.

According to the report from the Da Lat Area Construction Investment Project Management Board, the total public investment capital allocated in the year was nearly 416 billion VND, implemented on 52 projects. As of the end of June, the disbursement rate reached 48.11% (equivalent to nearly 200 billion VND). According to the Board's report, many projects are stuck in compensation and site clearance, especially the fact that the resettlement land price has not been determined.

In Lac Duong, the Lac Duong Area Construction Investment Project Management Board is implementing 22 projects with a total investment of more than VND89 billion. As of the end of July, the disbursement rate reached 17.4%, equivalent to VND15.47 billion. The project to upgrade and expand 19/5 Street in particular is facing difficulties due to the lack of consensus with some households on the compensation plan.

The meeting also recorded reports from ward representatives on land clearance mobilization work and related recommendations and proposals. Leaders of the People's Committees of Xuan Truong-Da Lat, Lam Vien-Da Lat, Xuan Huong-Da Lat wards also reported in detail on the progress of project implementation in the area.

Concluding the meeting, comrade Vo Ngoc Hiep emphasized: The disbursement rate of public investment capital for projects in Da Lat and Lac Duong areas is high compared to the provincial average. However, there are still problems that need to be resolved in each project. He also "named" a number of investment projects from the provincial budget that are still being delayed, such as the project from Lu Gia Street to the upper stream of Xuan Huong Lake, Hoang Van Thu Street, Yersin Park...

The Vice Chairman of the Provincial People's Committee also pointed out a number of problems and shortcomings and directed relevant units to focus on reviewing and evaluating each project, clearly identifying the locations of the problems to have timely solutions to remove them and promote project progress.
"From now until the end of the year, we must make efforts to disburse public investment capital for 2025 and capital transferred from 2024," Comrade Vo Ngoc Hiep emphasized.
For completed projects, urgently complete disbursement. For projects preparing for investment, promptly complete documents and submit to competent authorities for early approval of investment policies.

For unfinished construction projects, it is required to strictly implement the direction of the Provincial People's Committee leaders, closely review and speed up the progress of each project and each construction.
He also directed project investors to proactively coordinate with the People's Committees of wards and communes to do a good job of site clearance and resettlement arrangements for people affected by the projects.
Wards and communes must complete land prices for compensation and site clearance work within September.
Source: https://baolamdong.vn/thuc-day-tien-do-giai-ngan-von-dau-tu-cong-nam-2025-tren-dia-ban-da-lat-va-lac-duong-391520.html