According to official dispatch No. 07016/ UBND-CNXD, dated October 31, the People's Committee of Dak Lak province confirmed that the reflections of the Vietnam News Agency's Resident Office in Dak Lak province about the Central Highlands General Hospital project having been completed and put into use for many years but up to now the final settlement work has not been completed are correct.
The province determined that this is a backlog issue that has lasted for many periods. The main reason for the delay in settlement is that some legal documents and papers related to the project implementation process are incomplete or lost. There are problems and disagreements in determining the arising volume between the investor, the contractor and the consulting unit. In addition, there are some shortcomings in the management and handover of documents by the Project Management Board and the Department of Health (investor) over the periods.
After the VNA reporter informed that in order to completely resolve the difficulties and problems related to this issue, at the end of October 2025, the Dak Lak Provincial People's Committee assigned the Provincial Inspectorate to carry out an inspection of the Central Highlands General Hospital project according to regulations. The inspection will clarify the violations, infractions and shortcomings of related individuals and groups, on that basis, handle responsibilities according to regulations, speed up the settlement of project completion, and at the same time thoroughly overcome current difficulties and problems, in order to improve the quality of health examination for the people.
Dak Lak Department of Health has also invited contractors to work to reconfirm the volume and figures of unapproved final settlement packages of the Central Highlands General Hospital project.
Previously, as reported by VNA on September 17, the Central Highlands General Hospital with a scale of 1,200 beds was started in 2010 with a total investment of nearly VND1,100 billion. The project was invested by the Dak Lak Department of Health and completed and put into use at the end of February 2019. However, up to now, after more than 6 years of being put into use, the hospital has not been granted an official operating license because the project has not completed final settlement. This situation has forced the hospital to use a temporary operating license and this license has been extended many times. In addition, the hospital has not completed legal procedures on the environment due to the lack of environmental impact assessment reports and many related records and papers.
In addition, because many hospital construction items have not yet been finalized, there is not enough basis to determine that they are state assets formed from the project. This situation makes the repair, renovation, adjustment, and addition of items to meet the medical examination and treatment needs of the people not have enough legal basis to implement.