Resolutely resolve the problems of four important projects on the North-South Expressway

The Government Office issued Document No. 7310/VPCP-CN conveying the direction of Permanent Deputy Prime Minister Nguyen Hoa Binh - Head of Inspection Team No. 1 on urgently reviewing and removing difficulties and obstacles related to 4 key transport projects scheduled to be completed in 2025 under Inspection Team No. 1.

Báo Đầu tưBáo Đầu tư29/12/2024

Construction on the Hoa Lien - Tuy Loan expressway. (Photo: VGP/Luu Huong)
Construction on the Hoa Lien - Tuy Loan expressway. (Photo: VGP/Luu Huong)

The document stated: According to the proposed progress, the 4 North-South expressway projects of Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon, Hoai Nhon - Quy Nhon and Quy Nhon - Chi Thanh sections under Inspection Team No. 1 will open to technical traffic about 86.47 km/231.27 km on August 19, 2025; by the end of September 2025, about 114.7 km will be opened to technical traffic and the remaining 30.1 km will be completed in December 2025. To ensure the progress of completing the projects, Permanent Deputy Prime Minister Nguyen Hoa Binh , Head of Inspection Team No. 1, requested:

The provinces and cities of Da Nang , Quang Ngai, Gia Lai, and Dak Lak mobilized local authorities and functional agencies, especially the provincial police force, to organize construction protection at locations and sections where the land has been handed over but people obstructed the process of roadbed compaction and blasting; continue to organize construction protection according to the contractor's plan; at the same time, organize dialogue and propaganda so that people agree and support compensation policies according to regulations and commitments to compensation and support from investors and contractors.

In addition, continue to pay attention to and resolutely direct functional agencies and local authorities at all levels to focus on resolving difficulties and problems related to compensation, support and resettlement before August 15, 2025; assign focal units for investors and units participating in the Project to contact and coordinate in the process of implementing the remaining tasks of the Project.

The Deputy Prime Minister assigned Deputy Minister of Construction Nguyen Viet Hung to directly work with Da Nang city and Quang Ngai and Dak Lak provinces to urge and report to the Permanent Deputy Prime Minister.

The Ministry of Construction continues to direct investors and contractors to strictly control the progress, quality of works, traffic safety, labor safety, environmental sanitation, fire prevention and fighting during the construction process of contractors; promptly direct and handle difficulties and problems according to their authority so that projects can be completed on schedule.

Source: https://baodautu.vn/xu-ly-dut-diem-vuong-mac-bon-du-an-quan-trong-thuoc-tuyen-cao-toc-bac---nam-d352995.html


Comment (0)

No data
No data
Southeast Asian newspapers comment on the resounding victory of the Vietnamese women's team
Wild beauty on Ha Lang grass hill - Cao Bang
Vietnam Air Force practices preparing for A80
Missiles and combat vehicles 'Made in Vietnam' show off their power at A80 joint training session
Admire the million-year-old Chu Dang Ya volcano in Gia Lai
It took Vo Ha Tram 6 weeks to complete the music project praising the Fatherland.
Hanoi coffee shop is bright with red flags and yellow stars to celebrate the 80th anniversary of National Day September 2nd
Wings flying on the A80 training ground
Special pilots in the flying formation to celebrate National Day September 2
Soldiers march through the hot sun on the training ground

Heritage

Figure

Business

No videos available

News

Political System

Destination

Product