Admire the magnificent and massive Long Thanh airport after 3.5 years of construction

Báo Giao thôngBáo Giao thông28/05/2024


Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 1.

Started in May 2021, Long Thanh airport has been in operation for about three and a half years. Many items have been implemented such as drainage leveling, passenger terminal, runway, taxiway, and connecting road T1 T2.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 2.

From the vast rubber plantations, Long Thanh airport is now a huge construction site. The connecting roads are clearly visible, the terminal building is clearly shaped, and the runway is taking shape.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 3.

These items have helped Long Thanh airport become magnificent, massive, and different from before, especially when viewed from above.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 4.

According to the Vietnam Airports Corporation (ACV), there are currently nearly 6,000 officers, engineers and workers participating in the construction at Long Thanh airport.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 5.

Thousands of vehicles, machines and equipment are mobilized to speed up the project progress.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 6.

For the passenger terminal, the joint venture contractor has completed the underground part, finished the first floor slab, and is deploying formwork, steel reinforcement and concrete for the second floor slab. At this stage, workers are focusing on work, taking advantage of the sunny weather during the rainy season to pour concrete for the second floor slab.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 7.

Mr. Evren Isit Bingol, commander of the Vietur contractor consortium, said that the contractors have mobilized more than 3,220 workers and 950 pieces of equipment to focus on synchronously constructing items at the passenger terminal.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 8.

The station's progress is 10-20 days ahead of schedule in some items and the units are trying to complete the reinforced concrete structure early so that the steel roof structure can be erected at the end of the third quarter and the beginning of the fourth quarter.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 9.

Mr. Nguyen Chau (representative of contractor Vinaconex) said that because the South has entered the rainy season, construction work is more difficult. The contractor is still taking advantage of the sunny weather to continue to speed up progress.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 10.

Some jobs also require workers to work through the sun and rain to ensure volume.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 11.

For package 4.6 - runway construction, Mr. Le Van Tien (ACC Aviation Construction Corporation, the construction unit) said that the joint venture of contractors mobilized 1,700 people and 350 pieces of equipment and machinery with 50 construction teams working continuously.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 12.

Up to now, the contractor has completed the foundation and the M150 cement concrete layer of the runway structure. The M350 cement concrete surface is also being deployed to pour test strips.

Chiêm ngưỡng sân bay Long Thành hoành tráng, đồ sộ sau 3,5 năm thi công- Ảnh 13.

At the construction site of the traffic intersection connecting T1 and T2 (package 6.12), the joint venture contractor has mobilized 630 personnel, 196 machines and equipment and deployed all construction teams simultaneously. Workers are filling K95 and K98 soil, some sections have been graded with crushed stone, and bored piles are being completed...



Source: https://www.baogiaothong.vn/chiem-nguong-san-bay-long-thanh-hoanh-trang-do-so-sau-35-nam-thi-cong-192240528162924768.htm

Comment (0)

No data
No data

Same tag

Same category

Unique mini jellyfish pet
The picturesque route is likened to a 'miniature Hoi An' in Dien Bien.
Watch the red Dragonfly Lagoon at dawn
Explore Phu Quoc primeval forest

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product