Specifically, Component Project 3 belongs to the Khanh Hoa - Buon Ma Thuot Expressway Construction Project Phase 1 and the Ho Chi Minh Road Construction Investment Project, Eastern bypass section of Buon Ma Thuot City (Eastern bypass project).
Both of these projects are invested by the Dak Lak Province Project Management Board for Investment in Construction of Transport Works and Rural Development (Board A).
Construction of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Construction Project Phase 1. |
In which, Component Project 3 has a total length of more than 48 km, with a total investment of more than 6,165 billion VND.
The project has 3 construction packages, with a total implementation value of more than 3,039 billion VND (equal to 70.78% of the contract value). The cumulative disbursement of the project to date has reached 70.84% of the total allocated capital.
The Eastern bypass project is more than 39 km long, with a total investment of more than VND 1,841 billion, the value of the implemented volume reaching nearly 90%, and the cumulative disbursement value reaching 80.31%.
In order for the projects to be completed on schedule and to practically welcome the 14th National Congress of the Party, at the construction site, the investor directed the construction units and related units to speed up the progress and urgently complete the remaining volume.
Regarding legal procedures, the investor is coordinating with relevant parties to check and review in accordance with legal regulations.