Site clearance work for the Thuan An bridge approach road area has not yet reached the plan. |
Removing obstacles
The coastal road and Thuan An estuary overpass project (DA) phase 1 is invested by the Hue City Traffic Construction Investment Project Management Board. The project has a total investment of VND 2,400 billion, started construction in March 2022, with a construction period of 3 years by the joint venture of Tan Nam Construction Joint Stock Company - Dat Phuong Group Joint Stock Company - 479 Hoa Binh Company. The route is nearly 8km long, of which the bridge is about 2.36km long, the cross-section of the route is 26m, and the width is 20m.
Up to now, the total capital allocated for the project is more than 2,141 billion VND. Of which, 20 billion VND is local capital in 2025 and more than 354 billion VND is central capital transferred from 2024. The total disbursed capital of the project is more than 1,980 billion VND; of which, more than 234.7 billion VND was disbursed in 2025, reaching about 62.66%. The Thuan An seaport overpass project is expected to be completed by the end of 2025. After a recent inspection of the project's site clearance progress, Vice Chairman of the City People's Committee Hoang Hai Minh gave specific instructions on removing obstacles in site clearance work. Currently, the investor and construction units are making efforts to speed up the construction progress of the road section leading to Thuan An ward, ensuring the completion of the project according to the extended contract schedule.
According to the Project Management Board, the scope of land acquisition for phase 1 of the project is in Hai Duong commune and Thuan An ward (old), now Thuan An ward. For Thuan An ward in particular, the land acquisition has been organized for about 1.1km/2.3km of the entire access road. Specifically, the 600m section (map sheet 1,2) has been completed and the site has been handed over to the construction unit and the road surface has been paved with asphalt for 400/600m; the 500m section (map sheet 3) has 69 cases affected by the project, all households have handed over the site to the State for project construction, ensuring the route from Thuan An bridge to Hoang Sa intersection.
For the remaining sections, the land acquisition scope of map sheets 4 and 5 has 97 cases, currently 96/97 cases have been approved; there is 1 case that has not been approved, which is Ms. Pham Thi Ben. Due to the process of declaring the documents, the household provided the land use right certificate that was not correct for the recovered land plot, so the People's Committee of Thuan An Ward could not confirm the origin of land use. On August 25, 2025, the People's Committee of Thuan An Ward issued an approval decision for the remaining 33 cases of map sheets 4 and 5. The investor has transferred the funds, the Investment and Construction Project Management Board of Area 1 is proceeding with the procedures for compensation payment to households that have fully met the procedures and policies on compensation, support and resettlement (TDC).
To get projects to the finish line soon
Mr. Nguyen Tran Nhat Tuan, Director of the Investment and Construction Project Management Board of Area 1, said that in the coming time, the unit will urgently complete the compensation payment procedures for the remaining households. For households that have received money and fully implemented the compensation, support and resettlement policies, the Project Management Board will coordinate with the People's Committee and the Vietnam Fatherland Front Committee of Thuan An Ward to encourage households to hand over the site as soon as possible to speed up the project implementation progress. The current problem is that the land fund in the B5 resettlement area is not enough and not suitable for handing over to households that meet the resettlement conditions. Therefore, the unit only approves the plan that meets the conditions for resettlement arrangement. Regarding this issue, the Project Management Board has sent a document to the City People's Committee requesting the policy to adjust the B5 resettlement area project belonging to the infrastructure of the new urban area of Thuan An.
For the Hue City Cultural Sports Square Project, after the site clearance problems were resolved, the construction units accelerated the implementation progress. Thanks to that, in early September, the technical infrastructure items outside the project were inaugurated and put into use. This is a project of important significance, not only contributing to the orientation of urban space development, harmoniously connecting the landscape architecture system, creating new highlights for public space but also playing a role in promoting socio -economic development, improving the spiritual and physical life of the people. The City Cultural Sports Square Project has a total investment of 196 billion VND, with implementation time from 2024 to 2026. The project investment scale includes 2 main construction items: package 10 - external technical infrastructure and package 11 - renovation of the internal gymnasium.
Mr. Dang Quang Ngoc, Deputy Director of the City Urban Development and Construction Investment Project Management Board - the project investor, said that for the remaining items of the project, which is the renovation of the indoor gymnasium, the investor will strive to complete them in the coming time, putting all items of the project into effective use.
Member of the City Party Committee, Permanent Vice Chairman of the City People's Committee Nguyen Thanh Binh, in a recent inspection of the project, requested departments, branches, localities, and investors to urgently continue to speed up the progress of the remaining construction items to soon complete the entire project and put it into use, ensuring the goals, quality, aesthetics, safety, and full compliance with State regulations on investment and construction management.