Speeding up the progress of the Khanh Hoa - Buon Ma Thuot Expressway Project and the Ho Chi Minh Road Eastern bypass

On the morning of July 24, Vice Chairman of the Provincial People's Committee Truong Cong Thai chaired a direct and online meeting to listen to and direct the acceleration of the implementation progress and resolve difficulties and problems of Component Project 3 of the Khanh Hoa - Buon Ma Thuot Expressway Construction Project Phase 1 (referred to as Component Project 3) and the Ho Chi Minh Road Construction Investment Project, Eastern bypass of Buon Ma Thuot City, Dak Lak Province (referred to as the Eastern bypass Project).

Báo Đắk LắkBáo Đắk Lắk24/07/2025

According to the report of the investor of the two above projects, the Dak Lak Province Management Board of Traffic Construction Investment and Rural Development Projects (Board A), the total value of Component Project 3 (total of 3 construction packages) is currently more than VND 2,577 billion (equal to 61.14% of the contract value), 27.88% behind schedule and behind schedule as committed to be completed before August 30, 2025.

Vice Chairman of the Provincial People's Committee Truong Cong Thai chaired the meeting.

The reason is that the area the route passes through this year has had early, heavy and continuous rain, affecting the construction plans and progress of contractors; construction materials of sand and stone are scarce on the market, especially sand; the licensing time for Hoa Tien earth and stone quarry is slow and prolonged; some locations are still stuck, technical infrastructure has not been relocated (such as: TL10 intersection, branch 2 of CT02 intersection, road at the beginning of residential bridge 4, residential electricity system).

The project's cumulative disbursement to date is more than VND 2,965 billion (equal to 68.73% of the total allocated capital), of which the disbursement of the 2025 capital plan is more than VND 693 billion (equal to 33.9% of the plan).

Representative of the leadership of the Project Management Board for Investment in Construction of Traffic Works and Rural Development of Dak Lak Province reported at the meeting.
Representative of the leadership of the Project Management Board for Investment in Construction of Traffic Works and Rural Development of Dak Lak Province reported at the meeting.

For the Eastern Bypass Project, as of July 23, 2025, the site clearance and handover to the contractor for construction of the main route is about 39.5 km/39.6 km (128.75 ha); the remaining 0.113 km (0.35 ha) in Cuor Dang commune has not been cleared. Currently, there are 5 households whose plans have not been approved, of which 2 households are holding appraisal meetings, 3 households newly added to the planning are currently carrying out land recovery procedures according to regulations.

Up to now, the project is being implemented with 2 construction packages, the output is more than 836 billion VND (equal to 84.9% of the contract value).

live meeting combined with online
The meeting was held in person and online to relevant localities. (Screenshot) .

The cumulative project disbursement value to date is more than VND 1,453 billion (equal to 78.94% of the total allocated capital), of which the 2025 capital plan has disbursed more than VND 71 billion (equal to 17.29% of the plan).

Representatives of the Department of Agriculture and Environment contributed comments at the meeting.
Representatives of the Department of Agriculture and Environment contributed comments at the meeting.

Concluding the meeting, Vice Chairman of the Provincial People's Committee Truong Cong Thai requested project investors to preside over and coordinate with departments, branches, units and localities to handle issues related to material mines and relocation of technical infrastructure; review and work with sand mining units to resolve the lack of sand of the contractor in charge of Construction Package No. 3 of the project; guide the completion of procedures for handing over the project's excess material storage sites for management according to regulations.

In addition, units need to step up propaganda and mobilization work for people, be flexible in site clearance, and urgently carry out payment and refund procedures to speed up the disbursement of public investment capital.

Source: https://baodaklak.vn/kinh-te/202507/day-nhanh-tien-do-du-an-cao-toc-khanh-hoa-buon-ma-thuot-va-duong-ho-chi-minh-doan-tranh-phia-dong-ed90548/


Comment (0)

No data
No data
The powerful formation of 5 SU-30MK2 fighters prepares for the A80 ceremony
S-300PMU1 missiles on combat duty to protect Hanoi's sky
Lotus blooming season attracts tourists to the majestic mountains and rivers of Ninh Binh
Cu Lao Mai Nha: Where wildness, majesty and peace blend together
Hanoi is strange before storm Wipha makes landfall
Lost in the wild world at the bird garden in Ninh Binh
Pu Luong terraced fields in the pouring water season are breathtakingly beautiful
Asphalt carpets 'sprint' on North-South highway through Gia Lai
PIECES of HUE - Pieces of Hue
Magical scene on the 'upside down bowl' tea hill in Phu Tho

Heritage

Figure

Business

No videos available

News

Political System

Local

Product