Speeding up the progress of the Ho Chi Minh City Ring Road 3 Project through the province

The Ho Chi Minh City Ring Road 3 project, section through Tay Ninh province (component project 7), is focusing resources to speed up construction progress, ensuring the basic completion of the expressway section in October 2025, and the entire project in 2026 in accordance with the Government's direction.

Báo Long AnBáo Long An05/08/2025

The province strives to complete the expressway section in October 2025 and complete the entire Ho Chi Minh City Ring Road 3 project, the section passing through the province, in 2026.

The entire Ho Chi Minh City Ring Road 3 is about 76.34km long, passing through Ho Chi Minh City, Dong Nai and Tay Ninh provinces, divided into 8 component projects, of which the section passing through Tay Ninh province belongs to component project 7, about 6.84km long.

Component 7 project has a total investment of 3,040 billion VND, expected to be basically completed in 2025, put into operation from 2026. According to Mr. Tran Thien Truc - Deputy Director of Long An Construction Investment Project Management Board, by the end of July 2025, the project will be deployed in many packages simultaneously. Of which, 3 main packages (XL1, XL2, XL3) have positive progress, with construction volume reaching about 79.3% of contract value.

Package XL1 (expressway construction) has completed the treatment of weak soil, basic construction of crushed stone layer, asphalt paving and construction of Rach Rich bridge. It is expected to be fully completed and technically open to traffic by October 31, 2025.

Package XL2 (construction of viaduct, river crossing and parallel road) also recorded positive progress with more than 78% of the contract value. The main bridge items have completed most of the girders and pillars and are currently paving the bridge deck. The parallel sections on both sides have been paved with crushed stone, filled with sand and installed with drainage systems.

Package XL3 (construction of the final intersection connecting Ben Luc - Long Thanh Expressway) has reached 79.64% of the contract construction value and will be completed in October 2025. In addition, additional packages such as XL3A (completion of intersection), XL5 (traffic safety, fences, lighting) and XL4A, XL4B (connecting people's lives) are being actively implemented. The Intelligent Transport System (ITS) package is being prepared and is expected to be constructed in the third quarter of 2025.

Workers are working hard to construct Ring Road 3 in Ho Chi Minh City.

The technical infrastructure relocation work has also achieved many positive results, completing 8/11 medium and low voltage power relocation locations, continuing construction on Tan Long lines, Provincial Road 830C, branch L. The work of raising the clearance of the 500kV high voltage power line is under construction and will be completed in December 2025.

“The total capital allocated to implement component project 7 to date has reached VND2,252 billion, including central and local capital. Of which, 100% of the capital plan for 2023 and 2024 has been disbursed; in 2025, VND238.6 billion has been disbursed, reaching 27.22% of the plan” - Mr. Tran Thien Truc informed.

In particular, the section connecting to Ben Luc – Long Thanh Expressway was completed and handed over to VEC on May 15, 2025. Ben Luc – Long Thanh Expressway organized a site inspection on July 31, 2025 to prepare for traffic opening.

With the close direction of the Government , the close coordination between the Central and local levels, and the efforts of investors and construction units, the Ho Chi Minh City Ring Road 3 project through the province is being urgently and resolutely implemented.

The main packages are all on schedule, with some items expected to shorten the construction time by 1 to 3 months. Capital disbursement is well controlled, ensuring a continuous flow of capital for construction.

The province has identified this as not only an infrastructure investment task but also a regional development goal, creating a boost for the local socio-economic development. With high determination, the project will basically complete the expressway section by October 2025, the entire project will be completed in 2026, contributing to realizing the strategic vision of urban, industrial and logistics development in the Southern region./.

Le Duc

Source: https://baolongan.vn/day-nhanh-tien-do-du-an-vanh-dai-3-tp-hcm-doan-qua-dia-ban-tinh-a200111.html


Comment (0)

No data
No data

Same tag

Same category

Vietnam wins Intervision 2025 music competition
Mu Cang Chai traffic jam until evening, tourists flock to hunt for ripe rice season
The peaceful golden season of Hoang Su Phi in the high mountains of Tay Con Linh
Village in Da Nang in top 50 most beautiful villages in the world 2025

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product