The shape of the 150 billion VND C-shaped overpass about to open to traffic in Hanoi

Báo Thanh niênBáo Thanh niên14/05/2023


An official from the Hanoi Traffic Construction Investment Project Management Board (investor) said that up to now, the contractor has completed the structure of the C-shaped overpass, including many abutments and pillars. 9/9 steel girder structure spans have been erected; concrete has been poured on the bridge deck, and the embankments and railings are being installed.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 1.

Overview of the C-shaped overpass at present

According to the plan, the concrete deck of the entire bridge is expected to be completed in May. In June, the embankment, steel railings, traffic lighting, and drainage on the bridge will be completed; the asphalt concrete pavement will be completed. After that, the bridge will be tested for load, and the construction of the curb under the bridge, planting trees in the curb, and the asphalt concrete pavement will be completed. It is expected that on June 25, traffic organization will be completed and the project will be opened to traffic.

According to Thanh Nien , the shape of this bridge has been revealed. On both sides of the bridge, workers are gradually removing the corrugated iron fences and completing the final stages.

The C-shaped overpass was built from Pham Ngoc Thach Street to Chua Boc Street, with a total investment of 147.28 billion VND. The bridge has a reinforced concrete slab and a steel box girder structure, more than 320 m long.

The project is being implemented with the aim of improving traffic capacity at the Chua Boc - Pham Ngoc Thach - Ton That Tung - Dong Tac intersection (Dong Da District). This is a route that often experiences traffic congestion. The project has been under construction since October 2021, by a consortium of contractors including Thanh Long Group Joint Stock Company, Cienco1, and Viet Hung Technical Construction Joint Stock Company. However, due to many difficulties during the construction process, the project has been delayed 3 times.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 2.

The bridge surface is being completed.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 3.

C-shaped overpass section passing through Pham Ngoc Thach - Chua Boc intersection

The C-shaped overpass has a total investment of 147.28 billion VND.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 5.

Workers remove corrugated iron fences at the section passing through Chua Boc street.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 6.

The foot of the bridge is waiting to be poured concrete.

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 7.

The bridge has a reinforced concrete slab composite steel box girder structure, steel girder height 1.2 m

Hình hài cầu vượt chữ C 150 tỉ đồng sắp thông xe ở Hà Nội - Ảnh 8.

Workers are installing railings for the bridge.

The C-shaped bridge construction area is still congested during rush hour.



Source link

Comment (0)

No data
No data

Same tag

Same category

Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition
Mu Cang Chai traffic jam until evening, tourists flock to hunt for ripe rice season

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product