- On the afternoon of November 4, comrade Dinh Huu Hoc, member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee chaired a meeting to review the plan to implement site clearance for key projects in Dong Kinh ward.
Attending the meeting were comrade Phung Quang Hoi, member of the Provincial Party Standing Committee, Secretary of the Dong Kinh Ward Party Committee; leaders of a number of relevant departments and branches.

According to the report of the Provincial Construction Investment Project Management Board, the Ly Thai To Road extension project and the residential and resettlement area of Lang Son city have a total area of 24.51 hectares. The total number of households affected by the project is 550 households, 4 organizations, and 3 residential communities. Currently, the project site clearance work is still facing many difficulties, the handed over site area is small (2.6 hectares) , not qualified for construction .

The Ky Cung Riverbank Erosion Prevention Project has a total length of 2.97km (the section through the old Lang Son city is 2.05km long; the section through the old Loc Binh town is 0.92km long). The total land area recovered by the project is over 52.4 hectares. The project has established a record of compensation and support for all 109 households and 2 organizations, reaching 100%. Currently, 32 households have handed over the land in advance with an area of over 13.4/52.4 hectares. reached 25.70%.
For the Lang Son Provincial Sports Complex project (items: central stadium, multi-purpose gymnasium), the land use area of the project is 29 hectares. Relevant units declared and prepared compensation and support records for 143/200 households and individuals with an area of 15.8 hectares.

With the Huu Nghi - Chi Lang border gate expressway project under the BOT form, the section passing through Dong Kinh ward , the relevant agencies have completed the measurement and counting of 934/934 households, reaching 100%; completed the compensation payment and advance payment reaching 100%. Currently, on the section passing through the ward, there are still 12 locations where households have not relocated their houses to hand over the construction site.

At the meeting, leaders of relevant departments, branches, units and leaders of Dong Kinh ward reported and clarified the causes, difficulties and obstacles affecting the progress of site clearance and construction of projects; proposed solutions to promptly handle the problems, and committed to the completion time of related tasks.

In his concluding remarks at the meeting, the Standing Vice Chairman of the Provincial People's Committee requested the Provincial Construction Investment Project Management Board and Dong Kinh Ward to fully absorb the opinions at the meeting; complete the plan to implement the coordination work to achieve the highest efficiency.
He requested that relevant departments, branches and units need to follow the principle of clearly identifying the person in charge and the person supervising the implementation of site clearance work. At the same time, it is necessary to pay attention to propaganda work, ensuring specificity, details, clarity of work and content of propaganda, ensuring effectiveness, creating high consensus among the people; assigning experienced and specialized people to carry out site clearance work; proactively planning for arising situations. At the same time, pay attention to implementing the weekly periodic reporting regime according to each specific content and work progress; promptly propose and recommend difficulties and obstacles that need to be resolved...