The Provincial People's Committee has just issued a decision approving the adjustment of the investment project to build Dinh Khao bridge under the public-private partnership method.
Accordingly, the total investment excluding interest is adjusted to VND 2,761 billion, adding interest expense of more than VND 90.3 billion.
The Provincial People's Committee requests the Provincial Traffic Project Management Board (the inviting party) to coordinate with relevant agencies and units to promptly implement the project in accordance with the provisions of the Law on Investment under the public-private partnership method, relevant current legal provisions and take full responsibility for the accuracy and legality of the documents submitted for approval.
Previously, the Provincial People's Committee had approved the investment project to build Dinh Khao Bridge under the public-private partnership model. The project is about 4.3km long, invested in the scale of a level III plain road, with a design speed of 80km/h.
The expected project contract period is about 20.7 years (the project implementation period until the project is completed and put into use is about 3 years and the payback period according to the selected financial plan is 17.7 years).
Once put into use, the project will contribute to completing and improving the exploitation capacity of National Highway 57, overcoming traffic congestion at Dinh Khao ferry route, ensuring connection with the national highway and expressway system, shortening travel time with provinces in the Mekong Delta region, strengthening regional connectivity between provinces, opening up space for comprehensive development in the future.
KHANH DUY
Source: https://baovinhlong.com.vn/thoi-su/202511/dieu-chinh-bo-sung-noi-dung-tong-muc-dau-tu-cau-dinh-khao-c820270/






Comment (0)