![]() |
| As of October 28, 2025, Dong Nai province has disbursed nearly VND14 trillion in public investment capital. In the photo: Construction of Component 1 of the Bien Hoa - Vung Tau Expressway Project. Photo: Pham Tung |
In 2025, the total public investment capital plan allocated by the Provincial People's Committee (as of October 30, 2025) is nearly 37 trillion VND. Of which, the total public investment capital assigned by the Prime Minister is nearly 32 trillion VND, and Dong Nai province assigned an additional 5 trillion VND.
Thus, according to the public investment plan assigned by the Prime Minister, Dong Nai province has currently achieved a capital disbursement rate of more than 43% of the plan. If the planned capital of more than VND 9.2 trillion is not counted (including more than VND 8 trillion of the North-South Expressway Project, West section Gia Nghia - Chon Thanh, which the National Assembly allowed to extend the disbursement period until the end of 2026 and VND 1.2 trillion of newly assigned additional planned capital), the capital disbursement rate of Dong Nai province according to the plan assigned by the Prime Minister is more than 61%. This capital disbursement rate is higher than the average public investment disbursement rate of the whole country.
Also according to the Department of Finance, to achieve the target of disbursing 100% of public investment capital in 2025 as assigned by the Prime Minister, in the remaining time of the year, Dong Nai province must disburse the remaining capital of more than 8.8 trillion VND. According to the assessment, the remaining capital that needs to be disbursed in the last months of the year is relatively large, therefore, it requires determination and high concentration of departments, branches, investors, localities and related units.
To speed up the disbursement of public investment capital in the remaining time of 2025, the Department of Finance also recommended that departments, branches and localities coordinate to handle difficulties related to site clearance for projects. For projects that are no longer stuck in site clearance, it is necessary to speed up construction progress and provide equipment. Prepare materials to serve the construction of projects. For projects that have not yet been bid, investors should urgently complete the bidding documents and select contractors for the project.
Pham Tung
Source: https://baodongnai.com.vn/kinh-te/202511/dong-nai-giai-ngan-gan-14-ngan-ty-dong-von-dau-tu-cong-7040999/







Comment (0)