The project has a total investment of 3,010 billion VND. Of which, construction package 1 is worth 2,710.6 billion VND, with a contract implementation period of 240 days. According to the bidding minutes, the participating contractor is a consortium represented by Vietnam Construction and Import-Export Joint Stock Corporation.
Currently, the Ho Chi Minh Road Project Management Board is evaluating the bidding documents for Package TV12 Construction Supervision Consulting Package XL1, worth VND15,753 billion. The package attracted 2 bidders, including: Construction Technology, Equipment and Inspection Consulting Joint Stock Company (Coninco) and the Joint Venture of Traffic Construction Consulting Joint Stock Company 2 - Traffic Construction Consulting Joint Stock Company 5.
GIA MINH
Source: https://baodanang.vn/kinhte/202505/mo-goi-thau-xay-lap-hon-2700-ty-dong-doan-cao-toc-la-son-hoa-lien-4006510/