Việt NamViệt Nam02/01/2024

In the first days of the new year 2024, at the construction site of the East-West Road Construction Investment Project (Phase I), the working atmosphere is always bustling and urgent. This is a project that many people in the province are interested in and waiting for, because when the project is completed, it will open up development space for disadvantaged areas. After more than 1 year of construction, the project is being implemented on schedule. The shape of the large inter-regional and inter-provincial connecting road is gradually taking shape.

In recent days, the construction site of the East-West route project through Tam Diep city and Nho Quan district has always been bustling with trucks carrying materials, excavators, rollers... Hundreds of engineers and workers have been mobilized by contractors, divided into many construction teams to urgently implement the project. The first kilometers of the route have been basically completed, asphalted and connecting the first section of the East-West route to the intersection to Mai Son Expressway - National Highway 45.

Bustling on key construction project of East-West route
The first section has been paved with asphalt connecting to the Mai Son-National Highway 45.

Looking at the new, wide road that is about to be put into use, Mr. Nguyen Van Truong, a resident of Quang Son ward, Tam Diep city, excitedly said: "The road passing through the city has a different appearance. This change is not only significant in terms of traffic but also marks the development of the locality. Witnessing the change of our hometown, we are very excited. Hopefully, when the road is completed, it will continue to create momentum for socio -economic development for the young city."

According to comrade Pham Quoc Chinh, Director of the Provincial Traffic Construction Investment Project Management Board: The East-West route construction investment project with a total length of 23km from Tam Diep (at Dong Giao intersection, Quang Son commune) to Nho Quan (intersection with National Highway 12 in Van Phong commune) with an initial scale of 4 lanes according to class II road standards (the first section of the route to the North-South expressway intersection with a length of 1.64km is invested with a scale of 8 lanes according to Tam Diep urban planning) . This is the largest inter-regional traffic connection project ever in Ninh Binh province, of important significance in gradually completing the traffic infrastructure according to the Kim Son - Nho Quan route planning; connecting between expressways, national highways, provincial roads, tourist areas, industrial parks, industrial clusters in Tam Diep city, Nho Quan district and neighboring areas. Create space and land funds to attract investors to local strengths, contributing to socio-economic development and improving people's lives.

Bustling on key construction project of East-West route
Sunny weather creates favorable conditions for road construction.

Regarding the site clearance work on the route, up to now, the localities have handed over 20.2/22.9km of the site. Of which, the project scope in Tam Diep city has a length of 6.627km. Up to now, 6.627/6.627km has been handed over, however, within the handover scope, there are still 7 households with residential land that have not handed over their houses, architectural assets and within the handover scope, there are still problems with site clearance at some power line locations.

Bustling on key construction project of East-West route
Problems with site clearance in Phu Long commune, Nho Quan district.

The Project scope in Nho Quan district is 16.323km long; affected land area is 128.65ha. Up to now, 13.64/16.3km of agricultural land has been handed over (reaching about 83.66% of the cleared area), currently there are still problems with residential land, garden land, and some public works.

Regarding construction work, the East-West Road Construction Investment Project in Ninh Binh Province (Phase I) is being constructed by the Construction Joint Venture of Xuan Truong Construction Enterprise and Thanh Trung Company Limited. The project started in March 2022.

Mr. Le Anh Tu, Director of Thanh Trung Company Limited, representing the contractor, said: Currently, the contractor is actively implementing the construction. Taking advantage of the sunny weather, the contractor has focused all machinery, human resources, and materials for construction, the construction atmosphere at the construction site is very bustling, urgent, and highly focused. In addition, the consulting and supervising contractor and the investor are always present at the construction site to supervise the construction quality, techniques, and ensure the proposed progress.

Bustling on key construction project of East-West route
Thanh Trung Company Limited is focusing on machinery and human resources to speed up progress.

Bustling on key construction project of East-West route
Many roads are being paved with asphalt.

Currently, the construction unit is implementing the roadbed construction on the area of ​​20,267/22,927km of handed-over land. The asphalt paving has basically been completed and the first section of the East-West route connecting with the intersection to Mai Son Expressway - National Highway 45 has been connected. Contractors are focusing on constructing 70/110 cross-road culverts. The Ma Chanh, Song Van, Xuan Vien bridges have basically been completed, the bridge deck and railings are being completed; the Goc Sung 2 bridge has been constructed with 6 bridge girders.

Bustling on key construction project of East-West route
Ma Chanh Bridge is under construction and is basically completed.

The investor also said: For the roadbed materials, it is determined from 2 sources: coordinated along the route from Ma Chanh Hill at Km7 - Km8 to Km15+520 and purchased from Song Cau mine, in Yen Son commune (Tam Diep city), the mine closest to the Project to serve the fill from Km15+520 to the end of the route, the transportation route is in the direction of National Highway 12B to the construction site with a short transportation distance of only 13-14.5km.

Bustling on key construction project of East-West route
Strive to put the project into operation in 2025.

Up to now, the value of the Project implementation has reached about 35% compared to the contract. In order to soon put the project into operation and promote the effectiveness of the Project, the Investor is coordinating with relevant units to direct the acceleration of progress, striving to put the project into operation in 2025.

Nguyen Thom-Nguyen Luu-Truong Huy


Source

Comment (0)

No data
No data

Same tag

Same category

Discover the only village in Vietnam in the top 50 most beautiful villages in the world
Why are red flag lanterns with yellow stars popular this year?
Vietnam wins Intervision 2025 music competition
Mu Cang Chai traffic jam until evening, tourists flock to hunt for ripe rice season

Same author

Heritage

Figure

Enterprise

No videos available

News

Political System

Destination

Product